Foundation Inspection: Pass on First Try
The foundation inspection is one of the most critical in your entire build.
Get this wrong and you'll have problems for the life of the house. Get it right, and you're building on solid ground—literally.
Here's everything you need to know to pass on the first attempt.
NEVER backfill before inspection. This is the #1 failure point. Once backfilled, you'll have to excavate the entire perimeter at a cost of $2,000-$5,000. Mark your calendar. Put up signs. Tell your excavator. DO NOT BACKFILL.
When to Schedule
Timing: After foundation walls are complete but BEFORE backfilling
Critical: You must call for this inspection before any backfill. Once backfilled, the inspector can't verify the foundation exterior.
Notice required: 24-48 hours typically
Schedule for early in the week (Tuesday-Wednesday). This gives you time to fix issues before the weekend if you fail, keeping your project on track.
What the Inspector Checks
Foundation Walls
Concrete strength:
- Minimum 2,500 psi (3,000 psi in many areas)
- Check ready-mix tickets
- Inspector may require certified mix design
Wall thickness:
- Minimum 6" for 1-story
- Minimum 8" for 2-story
- Must match approved plans
Height above grade:
- Minimum 6" from finished grade to wood framing
- Many jurisdictions require 8"
- More in high-termite areas
Vertical and plumb:
- Walls must be relatively plumb
- Excessive bow or lean will fail
- Typically max 1" in 8' allowed
Footings
Size and depth:
- Minimum width per code (typically 16" for 1-story, 20" for 2-story)
- Depth below frost line (varies by location)
- Thickness (minimum 8" typical)
Reinforcement (if required):
- Rebar size and spacing
- Proper placement (not sitting on ground)
- Tied properly at corners
- Continuous around perimeter
Bearing on undisturbed soil:
- No loose soil, mud, or water in footing trench
- No organics (roots, stumps, debris)
- Soil type matches soil report
Anchor Bolts
Size: 1/2" diameter minimum (5/8" in high-wind or seismic zones)
Spacing:
- Maximum 6' on center
- Within 12" of plate ends
- Within 12" of each side of joints
Embedment: Minimum 7" into concrete
Thread exposure: Enough thread above nut for full engagement (typically 1/2")
Location: Centered in sill plate area
Waterproofing and Drainage
Dampproofing (below grade):
- Applied to exterior walls
- Continuous from footing to grade
- Type depends on soil conditions
Drainage system:
- Perimeter drain tile at footing
- Proper slope away from foundation
- Daylight or connection to sump
Gravel backfill:
- Clean gravel around drain tile
- Filter fabric over gravel
- Prevents clogging
Sill Plate Area
Termite barrier (if required):
- Metal termite shield
- Borate-treated sill plate
- Depends on termite zone
Gasket or sealant:
- Foam sill sealer
- Sealant under sill plate
- Required for energy code in most areas
Proper surface:
- Top of foundation level
- Anchor bolt holes properly located
- Clean of debris
Penetrations and Sleeves
Proper sleeves:
- Plumbing penetrations
- Electrical conduits
- HVAC penetrations
- Sized appropriately
Location:
- Not in structural weak points
- Proper height
- Match approved plans
Reinforcement (if required)
Vertical rebar:
- Size per plans
- Spacing per code
- Lap splices proper length
- Tied to footing rebar
Horizontal rebar:
- Top and bottom as required
- Proper cover (typically 3" minimum)
- Continuous around corners
Before the Inspector Arrives
Site Preparation - Before Inspector Arrives
During the Inspection
Checks Permit and Plans
Walks Perimeter
Inspects Footings
Counts Anchor Bolts
Checks Waterproofing
Inspects Penetrations
Reviews Paperwork
- Walk with the inspector - Don't disappear
- Answer questions honestly - They appreciate transparency
- Take detailed notes on any issues
- Don't make excuses - Just acknowledge and plan to fix
- Thank them for their time - Build a good relationship
Top 15 Failure Points
Based on a multitude of foundation inspections:
1. Backfilled Before Inspection
Failure: Owner backfilled to "get ahead" before inspection
Code requirement: IRC R401.3 - Inspector must see foundation exterior
Fix: Excavate entire perimeter. Expensive and embarrassing.
Cost: $2,000-$5,000 excavation + delay
Prevention: NEVER backfill before inspection. Mark your calendar. Put up signs. Tell excavator NOT to backfill.
2. Anchor Bolts Spaced Too Far
Failure: Bolts at 7-8' spacing when 6' max required
Code requirement: IRC R403.1.6 - 6' maximum spacing
Fix: Drill and epoxy additional anchor bolts
Cost: $300-$800 + 1-3 days delay
Prevention: Mark bolt spacing on forms before pour. Count off 6' maximum.
3. Insufficient Bolt Embedment
Failure: Bolts only 4-5" deep when 7" minimum required
Code requirement: IRC R403.1.6 - 7" minimum embedment
Fix: Drill and install new epoxied bolts, cut off old ones
Cost: $500-$1,500 + 3-7 days delay (epoxy cure time)
Prevention: Use bolt template. Verify depth during pour with a tape measure.
4. Foundation Too Close to Grade
Failure: Only 4" from grade to sill plate when 6" minimum required
Code requirement: IRC R401.3 - 6" minimum (8" in many areas)
Fix: Raise foundation walls, or lower grade significantly
Cost: If too low: $5,000-$15,000 to add height. Usually must demo and repour.
Prevention: Verify grade elevations before pour. Account for finish grade, not rough.
5. No Dampproofing
Failure: Forgot to dampproof below-grade walls
Code requirement: IRC R406.1 - Dampproofing required
Fix: Apply dampproofing before backfill
Cost: $500-$2,000 + 2-3 days delay
Prevention: Apply dampproofing before calling for inspection.
6. Missing or Improper Drain Tile
Failure: No perimeter drain installed
Code requirement: IRC R405.1 - Drainage required
Fix: Excavate, install drain tile and gravel
Cost: $2,000-$6,000 + 1-2 weeks delay
Prevention: Install drain tile at footing level before backfill. Verify slope.
7. Bolts Too Close to Edge
Failure: Anchor bolts within 1" of foundation edge
Code requirement: Minimum 2" from edge (typ), centered in sill plate
Fix: Drill and install new bolts in correct location
Cost: $300-$800 + delay
Prevention: Center bolts in sill plate area (typically 3-4" from edge).
8. Missing Bolts Near Corners
Failure: No bolt within 12" of plate ends/corners
Code requirement: IRC R403.1.6 - Within 12" of ends
Fix: Drill and epoxy additional bolts
Cost: $200-$500 + delay
Prevention: Mark corners and measure 12" for bolt placement.
9. Footing Too Shallow
Failure: Footing 18" deep when frost line is 36"
Code requirement: IRC R403.1.4 - Below frost line
Fix: Demolish and repour. No alternative.
Cost: $8,000-$20,000 + major delay (3-6 weeks)
Prevention: Know your frost depth. Verify before pouring. Stakes at proper depth.
10. Foundation Not Level
Failure: Top of foundation varies more than 1/2" over length
Code requirement: Must be reasonably level for framing
Fix: Grind down high spots, shim low spots, or pour mud-sill
Cost: $500-$2,000 depending on severity
Prevention: Use laser level during pour. Screed carefully. Check before concrete sets.
11. Wrong Concrete Strength
Failure: 2,000 psi mix when 2,500 psi required
Code requirement: IRC Table R402.2 - Minimum 2,500 psi
Fix: Usually requires structural engineer evaluation. May require replacement.
Cost: $2,000 engineer fee minimum. Potentially $15,000-$50,000 for replacement.
Prevention: Verify mix design before pour. Keep ready-mix tickets.
12. Honeycomb or Voids in Concrete
Failure: Significant voids or honeycomb in walls
Code requirement: Concrete must be solid, properly consolidated
Fix: Epoxy injection for small areas. Demolish and repour for major issues.
Cost: $500-$3,000 for epoxy. $5,000-$20,000+ for replacement.
Prevention: Proper vibration during pour. Don't use mix that's too dry.
13. Missing Reinforcement
Failure: No rebar in walls or footings when required by plans
Code requirement: Per approved structural plans
Fix: Usually requires engineer evaluation. May need to demolish.
Cost: $2,000+ for engineering. Potentially $10,000-$30,000+ for rebuild.
Prevention: Follow approved plans exactly. Double-check rebar before pour.
14. Improper Drainage Slope
Failure: Ground slopes toward foundation
Code requirement: IRC R401.3 - 6" drop in 10' away from foundation
Fix: Regrade after backfill
Cost: $1,000-$3,000 for regrading
Prevention: Plan finish grade before foundation. Verify with stakes and string line.
15. Penetrations Not Sleeved
Failure: Plumbing or electrical penetrations without proper sleeves
Code requirement: Penetrations must allow for movement, prevent water intrusion
Fix: Core drill and install sleeves, patch around pipe
Cost: $500-$1,500 per penetration
Prevention: Install proper sleeves before pour. 2-4" larger than pipe typically.
If You Fail
Don't Panic
Foundation inspection failures are common, even for professionals. Most are fixable.
Get Specifics
- What exactly failed?
- Code reference?
- How to fix correctly?
- Can I fix or need professional?
- Timeline for re-inspection?
Common Fixes and Costs
| Issue | Typical Fix | Cost | Time |
|---|---|---|---|
| Missing anchor bolts | Drill and epoxy bolts | $300-$800 | 3-7 days |
| No dampproofing | Apply dampproofing | $500-$2,000 | 2-3 days |
| No drain tile | Install drainage system | $2,000-$6,000 | 1-2 weeks |
| Foundation too low | Grade down or rebuild | $2,000-$15,000 | 1-6 weeks |
| Footing too shallow | Demolish and repour | $8,000-$20,000 | 4-8 weeks |
| Wrong concrete strength | Engineer eval/possible replace | $2,000-$50,000 | 2-12 weeks |
Re-Inspection Process
- Make ALL corrections (don't skip any items)
- Document fixes with photos
- Call for re-inspection
- Be present again
- Show inspector what you fixed
Timeline: Most re-inspections scheduled within 2-3 days for simple fixes.
Cost of Delay
Every day your foundation inspection is delayed costs money:
- Equipment rental: $200-$500/day (excavator, laser, etc.)
- Subcontractor delays: Framers scheduled but can't start
- Interest on construction loan: $50-$150/day
- Extended site security/insurance: $20-$50/day
A one-week delay = $2,000-$5,000 in holding costs
Prevention is way cheaper than delays. Count your anchor bolts the day before inspection. Verify no backfill. These simple checks save thousands.
Foundation Types: Special Considerations
Poured Concrete
Most common inspection points:
- Bolt spacing and embedment
- Wall thickness and height
- Reinforcement (if required)
- Proper mix strength
- Dampproofing and drainage
Block (CMU)
Additional checks:
- Properly filled cells
- Bond beam with reinforcement
- Vertical reinforcement in cells
- Cap blocks grouted
- Proper mortar joints
Permanent Wood Foundation (PWF)
Specific requirements:
- Pressure-treated lumber (proper treatment level)
- Proper fastener schedule
- Vapor barrier installation
- Gravel drainage
- Foundation-grade plywood
Slab-on-Grade
Different inspection (before concrete pour):
- Gravel base thickness and compaction
- Vapor barrier (6-mil minimum)
- Reinforcement placement
- Perimeter insulation (if required)
- Plumbing rough-in complete
Regional Variations
High-Wind Areas
Additional requirements:
- Larger anchor bolts (5/8")
- Closer spacing (4' OC)
- Hurricane straps/hold-downs
- Engineered foundation design
Seismic Zones
Additional requirements:
- Continuous foundation
- Proper reinforcement
- Hold-downs at shear walls
- Anchorage for concentrated loads
Flood Zones
Different requirements:
- Elevated foundation
- Flood vents
- Flood-resistant materials
- Proper elevation certification
High Water Table
**Additional requirements