Framing Inspection: Pass on First Try
The framing inspection is where structural integrity is verified.
This is your chance to prove the skeleton of your house is built to code—and it's one of the most detailed inspections you'll face.
Here's everything you need to pass on the first attempt.
All framing must be complete before calling for inspection, but no interior wall covering can be installed. Once you drywall, the inspector can't verify the framing. This is a common mistake that forces you to tear out drywall.
When to Schedule
Timing: After all framing is complete but BEFORE any wall covering (drywall, sheathing on interior)
Critical windows:
- All walls, floors, and roof structure must be complete
- All structural beams and headers installed
- Stair framing complete
- Fire blocking installed
- Structural sheathing on exterior is OK (inspectors expect it)
- Interior wall covering must NOT be installed yet
Notice required: 24-48 hours typically, up to 72 hours in busy seasons
Schedule for mid-week (Tuesday-Thursday). Gives you the weekend to finish any last-minute items, and you'll get re-inspection faster if needed.
Weather consideration: Inspectors will inspect in light rain but typically won't climb wet roofs. Have a backup date ready.
What the Inspector Checks
Structural Members
Dimensional lumber:
- Proper size for span (per approved plans and IRC span tables)
- Grade stamps visible on critical members
- No excessive defects (large knots, splits, warping)
- Proper orientation (load applied perpendicular to wide face)
Engineered lumber (LVL, PSL, LSL, I-joists):
- Proper size per manufacturer specs
- Installation matches manufacturer requirements
- No field modifications (cutting, notching)
- Proper bearing at supports
- Temporary bracing removed or verified
Beams and headers:
- Size matches approved plans
- Adequate bearing at each end (minimum 1.5" for sawn lumber, 3" for engineered)
- Properly connected to posts/walls
- No crushing of bearing surface
- Built-up beams properly fastened (if applicable)
Floor Framing
Joists:
- Proper size and spacing (per plans and IRC Table R502.3.1)
- Maximum span not exceeded
- Proper bearing at supports
- Blocking/bridging installed where required
- Cantilevers meet code limits (typically 4x joist depth)
Joist hangers:
- Correct size for joist dimension
- Every nail hole filled with proper hanger nail
- Installed right-side up
- Proper bearing on ledger or beam
Subflooring:
- Proper thickness (typically 23/32" for 16" OC joists)
- Glued and nailed per schedule
- Properly gapped for expansion (1/8" typical)
- Tongue-and-groove oriented correctly
Cantilevers and overhangs:
- Don't exceed code limits
- Properly reinforced/doubled where required
- Continuous rim joist
Wall Framing
Studs:
- Proper size (2x4 for single-story/non-load bearing, 2x6 for exterior in cold climates)
- Spacing matches plans (typically 16" OC)
- Top and bottom plates continuous
- Corners properly constructed (3-stud or 2-stud with drywall clips)
- Jack studs under headers
- King studs beside openings
- Cripples above/below openings as needed
Headers:
- Proper size for span and load
- Built-up headers properly nailed
- Resting on jack studs
- Proper support under bearing points
Shear walls (if required):
- Location matches plans
- Proper fastening schedule
- Hold-downs installed correctly
- No alterations from approved design
Wall height and plumb:
- Walls relatively plumb (within tolerance)
- Height matches plans
- Proper ceiling height maintained (minimum 7')
Roof Framing
Rafters (if stick-built):
- Proper size and spacing per IRC Table R802.5.1
- Proper bird's mouth cut (max 1/3 rafter depth)
- Ridge board adequate size (1" thicker than rafter)
- Collar ties at proper spacing (per code)
- Rafter ties to resist thrust
Trusses (if truss roof):
- Proper spacing
- Bracing installed per engineer's drawings
- No field modifications (critical!)
- Heel blocking installed
- Temporary bracing removed after permanent bracing complete
- Web bracing installed
Ceiling joists:
- Adequate size for span
- Connected to rafters for rafter ties (if conventional framing)
- Proper spacing
Roof sheathing:
- Proper thickness (typically 1/2" or 7/16" for 24" OC)
- Nailing pattern correct (6" edges, 12" field typically)
- H-clips installed for 24" spacing without tongue-and-groove
- Proper gapping for expansion
Connections and Fastening
Critical connections:
- Foundation to sill plate (anchor bolts with washers and nuts)
- Sill plate to floor system
- Floor system to walls
- Walls to roof system
- Beam to post connections (proper hardware)
Fastening schedule:
- Proper nail size and type
- Correct spacing
- Toe-nailing where specified
- Metal connectors properly installed
Hurricane ties/seismic ties (if required):
- Installed at every rafter/truss to top plate connection
- Correct type for wind/seismic zone
- All nail holes filled
Fire and Draft Stopping
Fire blocking (IRC R302.11):
- At 10' vertical in walls
- At soffits
- At cove molding spaces
- Between stories
- In furred spaces
Draft stopping (IRC R302.12):
- Floor/ceiling assemblies (every 1,000 sq ft)
- Attic spaces (every 3,000 sq ft)
Location: These are often forgotten. Mark them clearly before inspection.
Stairs
Stair framing:
- Stringers properly sized for span
- Minimum 3 stringers for 36" width
- Proper bearing at top and bottom
- Attached securely to structure
Dimensions:
- Maximum rise: 7-3/4" per IRC R311.7.5.1
- Minimum run: 10"
- Variation between risers: Maximum 3/8"
- Minimum width: 36"
- Minimum headroom: 6'8"
Landing requirements:
- Minimum 36" deep
- Width at least as wide as stairway
- Level (maximum 1/4" slope)
Before the Inspector Arrives
48 Hours Before Framing Inspection
Self-Inspection Checklist - Walk Through First
During the Inspection
Inspector's Typical Route
- Checks paperwork: Permit, approved plans
- Foundation connections: Anchor bolts, sill plate, rim joist
- Floor system: Joist size/spacing, hangers, blocking, subflooring
- Wall framing: Stud spacing, headers, corners, fire blocking
- Roof framing: Rafter/truss size, connections, bracing
- Stairs: Measures rise/run of each step
- Structural details: Beam bearing, critical connections
- Special items: Shear walls, hold-downs (if applicable)
Timeline: Expect 45 minutes to 2 hours depending on house size and complexity.
Your role:
- Walk with inspector (they may prefer alone in some areas)
- Answer questions about framing details
- Take notes on any concerns
- Ask for clarification on failures
- Don't argue or make excuses
- Thank inspector for their time and thoroughness
Top 15 Failure Points
Based on a multitude of framing inspections:
1. Missing or Improper Joist Hangers
Failure: Hangers missing nails, wrong size, or installed incorrectly
Code requirement: IRC R502.6 - All joints must be properly supported and connected
Specific issues:
- Not every nail hole filled (each hole must have a nail)
- Wrong size hanger for joist dimension (2x8 hanger for 2x10 joist)
- Using common nails instead of joist hanger nails
- Hanger installed upside down or sideways
- Hanger nails too long and poking through
How to fix: Replace incorrect hangers, fill all nail holes with proper hanger nails
Time to re-inspect: 2-4 days
Cost: $300-$800 (carpenter callback to fix hangers throughout house)
Prevention: Buy correct hangers, use only joist hanger nails, fill every hole, double-check before calling inspection
2. Headers Undersized or Improperly Supported
Failure: Header too small for span or not bearing on jack studs
Code requirement: IRC R602.7 - Headers must be sized per span tables
Specific issues:
- Header one size too small (4x8 when 4x10 required)
- Header spanning to king stud instead of jack stud
- Built-up header not properly nailed together
- No jack studs under header ends
- Header not bearing on full width of jack stud
How to fix: Install properly sized header with correct support
Time to re-inspect: 3-7 days (significant structural work)
Cost: $500-$2,000 depending on number of openings and complexity
Prevention: Calculate header sizes before framing, verify against IRC span tables, ensure jack studs under all headers
3. Missing Fire Blocking
Failure: Required fire blocking not installed in walls or concealed spaces
Code requirement: IRC R302.11 - Fire blocking required at specific locations
Where required:
- Walls at 10' vertical intervals
- Connection between horizontal/vertical concealed spaces
- Soffits and drop ceilings
- Cove molding areas
- Between floors
How to fix: Install 2x blocking or two layers 1x material at required locations
Time to re-inspect: 1-3 days
Cost: $200-$600 (if walls still open; much more if drywall started)
Prevention: Mark fire blocking locations during layout, install as you frame, verify before calling inspection
4. Improper Stair Dimensions
Failure: Stair risers or treads outside code requirements
Code requirement: IRC R311.7.5 - Specific stair dimension requirements
Requirements:
- Maximum riser: 7-3/4"
- Minimum tread: 10"
- Maximum riser variation: 3/8"
- Minimum width: 36"
- Minimum headroom: 6'8"
Common issues:
- Last riser different height (forgot to account for flooring)
- Inconsistent riser heights
- Insufficient headroom
- Winders don't meet minimums
How to fix: Rebuild stairs to correct dimensions
Time to re-inspect: 3-7 days
Cost: $800-$2,500 (complete stair rebuild)
Prevention: Carefully calculate rise/run before cutting stringers, verify actual floor-to-floor height including finish flooring, measure each riser/tread
5. Excessive Notching or Boring of Joists
Failure: Joists notched or drilled beyond code limits
Code requirement: IRC R502.8 - Specific limits on notching and boring
Limits:
- Notches: Maximum 1/6 depth at ends, 1/3 depth in middle third
- Holes: Maximum 1/3 depth, minimum 2" from edges, no closer than 2" to other holes
- Never notch middle third of span
- Never notch engineered lumber or I-joists
How to fix: Sister reinforcing joist alongside damaged member, or install full sister if severely compromised
Time to re-inspect: 2-5 days
Cost: $400-$1,500 depending on number of joists and accessibility
Prevention: Route plumbing and electrical properly, know limits before cutting, never let plumber/electrician cut without supervision
6. Insufficient Bearing for Beams
Failure: Beams don't have adequate bearing surface at supports
Code requirement: IRC R502.6 - Minimum 1.5" bearing for sawn lumber, 3" for engineered beams
Specific issues:
- Beam bearing on less than required width
- Beam overhanging post
- No positive connection between beam and post
- Bearing surface not level
- Posts not adequately sized for load
How to fix: Add proper bearing, install correct post caps, resize posts if needed
Time to re-inspect: 3-7 days (structural modification)
Cost: $400-$1,200 per beam/post connection
Prevention: Use post caps for all beam-to-post connections, measure bearing surface, ensure minimum bearing
7. Roof Truss Modifications
Failure: Any field modification to engineered roof trusses
Code requirement: IRC R802.10.3 - Trusses shall not be altered
What I see:
- Cut bottom chord for attic access
- Cut webs for HVAC duct
- Cut top chord for valley
- Notched or drilled anywhere
- Missing bracing per engineer drawings
How to fix: Usually requires structural engineer to design repair (expensive)
Time to re-inspect: 1-3 weeks (engineering time + repairs)
Cost: $2,000-$8,000 (engineering + reinforcement)
Prevention: NEVER cut trusses. Route all mechanicals around trusses. Get engineer involved before any modifications.
8. Missing Hurricane Ties or Seismic Clips
Failure: No hurricane ties connecting rafters/trusses to top plate
Code requirement: IRC R802.11 - Connection required per wind speed and seismic zone
Requirements vary by location:
- Basic wind speed determines connection strength
- Seismic zone determines requirements
- May need specific tie model (check approved plans)
- Must be installed on every rafter/truss
How to fix: Install proper ties at every rafter/truss location
Time to re-inspect: 2-4 days
Cost: $300-$1,000 (ties + labor to install on all rafters)
Prevention: Know your wind/seismic requirements, buy correct ties, install on every rafter as you frame roof
9. Improper Wall Bracing
Failure: Insufficient or incorrectly installed wall bracing
Code requirement: IRC R602.10 - Braced wall panels required
Methods (depends on seismic/wind zone):
- Let-in bracing at 45 degrees
- Structural sheathing panels
- Diagonal metal strapping
- Portal frames
Common issues:
- Not enough braced wall panels for building configuration
- Bracing doesn't meet length requirements
- Improper nailing of sheathing
- Let-in bracing not continuous
How to fix: Add additional bracing per code requirements
Time to re-inspect: 3-7 days
Cost: $500-$2,000 depending on amount needed
Prevention: Calculate bracing requirements before framing, follow approved plans, verify proper installation
10. Inadequate Headroom Over Stairs
Failure: Headroom less than 6'8" at any point along stairs
Code requirement: IRC R311.7.2 - Minimum 6'8" headroom measured vertically
How it happens:
- Ductwork installed too low
- Beam placed incorrectly
- Ceiling height not calculated properly
- Attic access door location
How to fix: Raise obstruction, reroute ductwork, or rebuild stairs with different pitch
Time to re-inspect: 3-7 days (can be complex)
Cost: $800-$3,000 depending on what's blocking
Prevention: Calculate headroom before building stairs, verify clearance at all points along stair run
11. Rafters with Improper Bird's Mouth
Failure: Bird's mouth cut removes too much material from rafter
Code requirement: IRC R802.7.1 - Notch depth shall not exceed 1/3 rafter depth
Typical requirement:
- Maximum bird's mouth depth: 1/3 of rafter depth
- Remaining rafter depth must be adequate for span
- Must bear on full width of top plate
How to fix: Sister rafters to reinforce if cut too deep, or replace rafters
Time to re-inspect: 3-7 days
Cost: $600-$2,000 (sistering or replacing rafters)
Prevention: Mark bird's mouth depth before cutting, verify against 1/3 depth rule, cut conservatively
12. No Blocking or Bridging Where Required
Failure: Missing blocking between joists or under bearing walls above
Code requirement: IRC R502.7 - Blocking required at bearing points
Where required:
- Under all bearing walls above
- At joist laps over beam
- Cantilever ends
- Joist runs over 8' (depending on jurisdiction)
How to fix: Install solid blocking at required locations
Time to re-inspect: 2-4 days
Cost: $300-$800 (accessing and installing blocking)
Prevention: Install blocking as you frame, mark locations on plans, verify before inspection
13. Subfloor Not Properly Fastened
Failure: Subfloor not glued and nailed per schedule, or improper spacing
Code requirement: IRC R503.2.1 - Fastening per approved plans and manufacturer
Requirements:
- Glued (construction adhesive) and nailed
- 6" OC at edges, 12" OC in field (typical)
- 1/8" spacing between sheets for expansion
- Tongue and groove oriented correctly
How to fix: Add additional fasteners, may require replacing sheets not glued
Time to re-inspect: 2-4 days
Cost: $400-$1,200 (labor to add fasteners)
Prevention: Glue every sheet, follow nailing schedule, use proper spacing
14. Openings Not Properly Framed
Failure: Window or door openings missing king studs, jack studs, or cripples
Code requirement: IRC R602.7 - Opening framing requirements
Proper framing:
- King studs full height each side of opening
- Jack studs (trimmers) supporting header
- Cripples above header to top plate
- Cripples below sill (windows)
- Double sill for wider windows
How to fix: Add missing framing members
Time to re-inspect: 2-4 days
Cost: $200-$600 per opening
Prevention: Follow standard framing practices, verify each opening has all required members
15. Built-Up Beams Not Properly Fastened
Failure: Doubled or tripled beams not nailed together properly
Code requirement: IRC R602.7.2 - Built-up beams must be fastened together
Requirements:
- Nailed together with proper schedule (typically 16d at 16" OC staggered)
- All layers of same dimension
- No gaps between layers
- Bearing on jack studs, not king studs
How to fix: Add fasteners to meet schedule
Time to re-inspect: 1-3 days
Cost: $150-$400 (labor to add nails)
Prevention: Nail built-up beams as you assemble them, don't rely on a few nails
If You Fail
Stay Calm
Framing inspection failures are common. Most are straightforward fixes.
Get Written Details
Ask inspector for:
- Specific code section violated
- Exact location of problem
- How to correct it properly
- Whether correction requires engineer review
Common Fixes and Timeline
| Issue | Fix | Cost | Timeline |
|---|---|---|---|
| Missing fire blocking | Install blocking in walls | $200-$600 | 1-3 days |
| Joist hangers incomplete | Add missing nails | $100-$300 | 1-2 days |
| Undersized header | Replace with correct size | $500-$2,000 | 3-7 days |
| Missing hurricane ties | Install all required ties | $300-$1,000 | 2-4 days |
| Stair dimensions wrong | Rebuild stairs to code | $800-$2,500 | 3-7 days |
| Cut or modified truss | Engineer design repair | $2,000-$8,000 | 1-3 weeks |
Re-Inspection Process
- Make all corrections noted (don't skip any)
- Take photos of corrections
- Call for re-inspection
- Be present for re-inspection
- Show inspector what was corrected
Re-inspection timing: Usually 2-4 days for scheduling
Cost of Delay
Each day framing inspection is delayed costs:
- Holding costs: Construction loan interest, insurance, etc. ($50-150/day)
- Subcontractor delays: Electrician, plumber, HVAC scheduled but can't start
- Weather risk: Longer exposure before weather-tight
- Cascade delays: Every trade after framing is now delayed
One week delay = $1,500-$3,000 in direct costs plus schedule disruption
Pass on first try by preparing thoroughly.
Special Considerations
Engineered Lumber
Special rules:
- Follow manufacturer installation instructions exactly
- Don't notch or drill I-joists (web knockouts only)
- Proper bearing and blocking required
- Temporary bracing often needed during installation
Inspector focus: They'll verify no field modifications
Shear Walls and Hold-Downs
If required (seismic/wind zones):
- Location must match approved plans exactly
- Proper fastening schedule critical (often closer spacing)
- Hold-down bolts must be installed correctly
- No deviation from engineered design allowed
Get engineer involved early if you need to change anything.
Post and Beam Construction
**Different inspection focus