The Permit Application Process: Your Complete Walkthrough
Getting your building permit approved doesn't have to be intimidating. This guide will walk you through every step of the application process, from initial planning to holding your approved permit in hand.
Realistic timeline: 8-16 weeks from start to permit issuance. Start this process 4-6 months before you want to break ground. Delays are common and expected.
Timeline Overview
Here's what to expect for the full permit process:
| Phase | Timeframe | Key Activities |
|---|---|---|
| Preparation | Weeks 1-2 | Document gathering, property research |
| Pre-Application Meeting | Weeks 3-4 | Meeting with building department, final prep |
| Submit Application | Week 4 | Submit complete application package |
| Plan Review | Weeks 5-10 | Department reviews (varies widely) |
| Corrections | Weeks 11-12 | Address feedback, resubmit |
| Final Approval | Weeks 13-16 | Permit issuance, ready to build |
Phase 1: Preparation (Weeks 1-2)
Before you even visit the building department, gather all necessary information.
Property Information Checklist
Survey and Site Information
Zoning and Restrictions
Utility Information
Complete Your House Plans
You'll need professionally drawn plans. Don't skimp here.
Architectural Plans ($2,000-$8,000):
- Site plan showing house location
- Floor plans (all levels including basement/attic)
- Elevations (all four sides)
- Cross-sections
- Roof framing plan
- Foundation plan
- Details and notes
Structural Plans ($500-$2,500 if needed):
- Beam calculations
- Header sizing
- Foundation design
- Engineered trusses (if used)
- Unusual spans or loads
MEP Plans (often included in architectural):
- Electrical plan with panel schedule
- Plumbing plan with fixture count
- HVAC plan with load calculations
- Gas line routing (if applicable)
Energy Calculations (free with REScheck):
- Energy code compliance report
- Insulation values
- Window specifications
- HVAC efficiency ratings
Don't try to save money with DIY plans. I've seen owner-builders waste months with incomplete or unclear plans. A good set of plans costs $4,000-$12,000 total and is worth every penny.
Phase 2: Pre-Application Meeting (Weeks 2-3)
Schedule the Meeting
Call your building department and request a pre-application conference. Most offer these for free.
What to Bring:
- Preliminary plans (even rough sketches)
- Site survey
- List of questions
- Notebook for taking notes
Critical Questions to Ask
| Category | Questions to Ask |
|---|---|
| Application Requirements | • Which version of the IRC do you enforce? • What local amendments apply? • Do you require engineer stamps? • What energy code compliance is needed? • Are there any site-specific concerns? |
| Fees | • What are the permit fees? (based on project value) • Are there impact fees? • Are there school fees or other add-ons? • What forms of payment do you accept? |
| Timeline | • What's the current plan review backlog? • How long until first review? • How many review cycles should I expect? • What's the typical correction turnaround time? |
| Inspections | • What inspections are required? • How much notice for scheduling? • Can I do rough-in inspections together? • What are common failure points? |
The relationship you build with the building department staff now will pay dividends throughout your project. Be respectful, prepared, and eager to learn.
Phase 3: Final Document Preparation (Week 3)
Complete Application Package
Required Forms
Required Plans (3-5 sets)
Calculations and Reports
Additional Documents
State-Specific Requirements
Requirements vary significantly by state. Here are common state-specific items you may need:
Florida:
- Product approval numbers for hurricane-rated items
- Wind load calculations
- Flood zone documentation
California:
- Energy compliance (Title 24)
- Seismic design
- Wildfire protection (WUI zones)
- Extensive environmental review
Texas:
- Drainage plan
- Windstorm certification (coastal areas)
- Foundation design for expansive soils
North Carolina:
- Soil erosion control plan
- Septic permit prior to building permit
- Energy code compliance
Phase 4: Submit Your Application (Week 4)
Pre-Submission Checklist
Before You Submit
At intake, applications are commonly rejected for:
- Incomplete forms
- Missing signatures
- Wrong number of plan sets
- Missing engineer stamps
- Incorrect fees calculated
Double-check everything before you go.
Submission Options
In-Person (recommended for first-timers):
- ✅ Immediate feedback on completeness
- ✅ Can ask questions
- ✅ Get receipt immediately
- ✅ Build relationship with staff
Online (if available):
- ✅ Faster, no waiting in line
- ✅ Upload documents
- ❌ May have file size limits
- ❌ Harder to get immediate feedback
Mail (least common now):
- ❌ Longest turnaround
- ❌ No immediate verification
- ❌ Risk of documents lost
Submit in person for your first time. The front desk staff can catch simple errors immediately and save you weeks of delay.
What Happens at Submission
Completeness Check (5-10 minutes)
Fee Calculation
Payment
Receive Tracking Info
Plans Enter Review Queue
Typical Permit Fees (2,000 sq ft home)
| Fee Type | Typical Cost |
|---|---|
| Building permit | $1,500 - $3,500 |
| Electrical permit | $200 - $500 |
| Plumbing permit | $200 - $500 |
| Mechanical permit | $150 - $400 |
| Plan review | $300 - $800 |
| Impact fees | $0 - $20,000+ |
| TOTAL TYPICAL COST | $2,500 - $6,000 |
Impact fees vary wildly and can add $0-$20,000+ to your costs. Always ask about these during your pre-application meeting.
Phase 5: Plan Review (Weeks 5-10)
What Happens During Review
Your plans will be reviewed by multiple departments in parallel:
| Department | Review Time | What They Check |
|---|---|---|
| Building Department | 2-4 weeks | Structural compliance, code adherence, energy code, accessibility |
| Electrical Review | 1-2 weeks | Panel sizing, circuit layout, GFCI/AFCI protection, service size |
| Plumbing Review | 1-2 weeks | Fixture units, vent sizing, drain sizing, water supply |
| Mechanical Review | 1-2 weeks | Load calculations, equipment sizing, ductwork design, combustion air |
| Other Departments | Varies | Fire marshal, health (septic), DOT (driveway), zoning, engineering |
Review Timeline Factors
Fast Review (2-4 weeks):
- Simple design
- Stock plans
- Off-season (winter)
- Small jurisdiction
- Complete, clear plans
Slow Review (6-12+ weeks):
- Complex design
- Custom home
- Busy season (spring/summer)
- Large jurisdiction
- Incomplete plans
- High permit volume
You can't control jurisdiction size, season, or volume. But you can control plan quality. This is where professional plans pay off.
Stay Productive During the Wait
While Plans Are in Review
Phase 6: Corrections and Resubmissions (Weeks 10-14)
You WILL Get Corrections
Even professionally drawn plans rarely pass on first submission. This is normal. Don't be discouraged.
Common Correction Requests by Trade
Structural:
- Clarify beam sizes
- Add span calculations
- Detail connections
- Show shear wall locations
- Specify fastener schedules
Electrical:
- Add circuit details
- Show panel location
- Clarify GFCI protection
- Add AFCI circuits (newer codes)
Plumbing:
- Show vent sizing
- Detail drain slopes
- Clarify fixture locations
- Show water heater specs
Energy:
- Update REScheck
- Clarify insulation values
- Add window specs
- Show air sealing details
Responding to Corrections
Review Correction List Carefully
Address EVERY Item
Make Changes Clearly on Plans
Prepare Response Letter
Resubmit Complete Package
I've seen projects delayed weeks because the owner-builder didn't address one "minor" item the reviewer listed. Address everything.
Phase 7: Approval and Permit Issuance (Weeks 14-16)
Final Approval Process
Once all corrections are satisfied:
- Plans are stamped "APPROVED"
- Permit is issued
- You pay any remaining fees
- You receive:
- Permit card (post at job site)
- Approved plan sets (keep one on site)
- Inspection card or schedule
- Any special requirements
Immediate Actions After Receiving Permit
Before Leaving Building Department
At Your Job Site
Permit Validity Period
Typical permit validity:
- Valid for: 6-24 months (varies by jurisdiction)
- Extensions: Usually available for a fee
- Expiration: If no progress, permit expires
- Renewal: Must reapply if expired
Keep your permit active:
- Start work within required timeframe (often 180 days)
- Complete inspections as you progress
- Don't let months pass without activity
Common Application Mistakes to Avoid
| Mistake | Better Approach | Cost of Mistake |
|---|---|---|
| Rushing the application with incomplete plans | Submit complete, high-quality plans | Delays add thousands in holding costs |
| Drawing plans yourself without experience | Hire professional draftsperson ($2,000-$8,000) | Months of delays, multiple resubmissions |
| Not meeting with building department first | Schedule pre-app meeting, take notes | Massive delays from wrong assumptions |
| Using wrong code version | Confirm code version with department first | Complete plan redesign ($5,000+) |
| Missing engineer stamps | Ask at pre-app, budget for stamps | Rush engineering fees + delays |
| Incomplete energy calculations | Run REScheck (free), include in submission | Delay costs add up quickly |
| Poor site plan without clear setbacks | Professional survey ($400-$1,000) | Automatic rejection, resubmit delays |
| Not budgeting for impact fees | Ask about ALL fees at pre-app meeting | $10,000-$20,000+ surprise |
Complete Permit Application Cost Breakdown
Professional Services
| Item | Cost Range | Notes |
|---|---|---|
| House plans | $2,000 - $8,000 | Don't skimp on this |
| Structural engineering | $500 - $2,500 | If needed for complex spans |
| Truss design | $300 - $800 | If using engineered trusses |
| Energy calculations | $0 - $300 | REScheck is free DIY |
| Site survey | $400 - $1,000 | Required, no shortcuts |
| Soil/percolation test | $500 - $1,500 | If septic system needed |
Permit Fees
| Fee Type | Cost Range | Notes |
|---|---|---|
| Building permit | $1,500 - $5,000 | Based on project value |
| Electrical permit | $200 - $500 | Separate fee usually |
| Plumbing permit | $200 - $500 | Separate fee usually |
| Mechanical permit | $150 - $400 | Separate fee usually |
| Plan review | $300 - $800 | Sometimes separate charge |
| Impact fees | $0 - $20,000+ | Highly location dependent |
| TOTAL TYPICAL | $6,000 - $40,000+ | For complete permit ready-to-build |
Plan for 2-3% of total build cost in permits and related fees.
Pro Tips From 15 Years of Permitting
1. Build Relationships Early
The building department staff will be your partners for 6-12 months. Treat them well from day one.
2. Over-Document Everything
More detail is always better. Unclear plans get rejected. Clear plans get approved.
3. Use the Off-Season
Submit November-February when departments are less busy. You'll get faster reviews and more attention.
4. Ask Questions Upfront
Never assume. Always verify with your specific jurisdiction. What's required in one county may not be in the next.
5. Budget Time Generously
Murphy's Law applies to permitting. Add 50% to your timeline estimate.
6. Keep Communication Records
Save all emails, letters, and meeting notes. You'll need them when questions arise.
7. Be Patient But Persistent
Weekly status checks show you're serious without being annoying.
Final Checklist: Ready to Submit?
Final Pre-Submission Verification
Next Steps
Understand Building Codes
Work Effectively with Building Department
Avoid Common Permit Mistakes
Review Main Permitting Guide
Our permit application consultation service includes plan review, application assistance, and guidance through the entire process. We'll help you avoid the mistakes that cause delays and thousands in extra costs.