Final Finishes: Complete Guide
Overview
- Typical Duration: 1-2 weeks
- DIY Difficulty: ⭐⭐☆☆☆ (2/5)
- Typical Cost: $3,000-$8,000
- When to Hire: Very DIY-able - mostly installation tasks
- Required Inspection: Final inspection required before occupancy
Final finishes transform your construction site into a move-in ready home. This phase involves dozens of small tasks - light fixtures, outlets, hardware, appliances, and addressing the punch list. While individually simple, the volume of tasks requires systematic organization.
This is one of the most satisfying phases. Each completed item brings you closer to occupancy, and progress is highly visible.
When This Phase Happens
Final finishes happen after all major work is complete.
Must be complete first:
- Painting complete
- Flooring installed
- Kitchen and bath complete
- All trim installed
What comes after:
- Final inspection
- Certificate of Occupancy
- Move-in!
Punch List Overview
What is a punch list? A systematic list of all remaining tasks, defects, and touch-ups required before the project is complete. Professional builders use punch lists on every project.
How to create your punch list:
- Walk through entire house with notebook
- Inspect every room systematically
- Note every incomplete item, defect, or touch-up needed
- Include exterior
- Organize by room or trade
- Estimate time for each item
- Prioritize for final inspection
Typical punch list items:
- Paint touch-ups
- Drywall repairs
- Trim adjustments
- Hardware installation
- Fixture installation
- Cleaning
- Caulking touch-ups
- Door adjustments
- Window operation checks
- Floor touch-ups
Step-by-Step Process
Days 1-3: Electrical Fixtures and Devices
Light fixture installation:
- Turn off power at breaker
- Connect fixture wires (black to black, white to white, ground to ground)
- Secure fixture to ceiling box
- Install bulbs and shades
- Test operation
- Repeat for all fixtures (typically 20-30 fixtures)
Outlet and switch covers:
- Install covers on all outlets and switches (typically 60-80)
- Ensure proper alignment (horizontal/vertical)
- Paint-grade: Use paintable covers, paint before installing
- Use screws provided with covers (not drywall screws)
Smoke and CO detectors:
- Install per code requirements (one per bedroom, one per floor, one outside sleeping areas)
- Connect to hardwired circuits (installed during electrical rough-in)
- Install backup batteries
- Test all detectors
- Link interconnected system (one sounds, all sound)
Exterior lighting:
- Install porch lights
- Install motion sensor lights (security)
- Install landscape lighting (if planned)
- Test all exterior outlets (GFCI protected)
Days 4-6: Plumbing Fixtures and Appliances
Final plumbing fixtures:
- Towel bars and toilet paper holders
- Shower rods or glass doors
- Medicine cabinets
- Soap dispensers
- Hand towel rings
Appliance installation:
Refrigerator:
- Slide into position (verify fit before removing packaging)
- Level front-to-back and side-to-side
- Connect water line for ice maker (if applicable)
- Plug in and test
Dishwasher:
- Slide into cabinet opening
- Level and secure to underside of counter
- Connect water supply line
- Connect drain line to disposal or drain
- Connect electrical (typically hardwired)
- Test operation, check for leaks
Range/Cooktop:
- Gas: Hire licensed professional for gas connection
- Electric: Verify proper 240V circuit, secure connection
- Slide into position
- Level
- Secure anti-tip bracket (code required)
- Test operation
Microwave (if over-range):
- Install mounting bracket
- Lift microwave into position (requires 2-3 people)
- Secure to wall and cabinet
- Connect electrical
- Install charcoal and grease filters
- Test operation
Washer/Dryer:
- Position in laundry area
- Connect water supply (washer)
- Connect drain (washer)
- Connect dryer vent (critical for safety - must vent outside)
- Connect dryer power (240V electric or gas line)
- Level both units
- Test operation
Days 7-9: Hardware and Accessories
Door hardware:
- Install doorknobs and deadbolts on exterior doors
- Install privacy locks on bedroom and bath doors
- Install passage sets on other interior doors
- Install door stops (floor or wall mount)
- Adjust strike plates for proper latching
- Ensure all doors open and close smoothly
Cabinet hardware:
- Install knobs or pulls on all cabinets (kitchen and baths)
- Use template for consistent placement
- Verify all doors and drawers align properly
- Adjust hinges as needed
Closet accessories:
- Install closet rods
- Install shelf brackets
- Install specialty organizers if planned
Window treatments (if providing):
- Install curtain rods or blinds
- Follow manufacturer instructions
- Level all rods
Days 10-12: Exterior Final Touches
Exterior items:
- Install house numbers (clearly visible from street - code requirement in many areas)
- Install mailbox (per postal service requirements)
- Install doorbell or video doorbell
- Install exterior door hardware (handlesets)
- Install garage door opener
- Test garage door safety sensors (required by code)
Gutters and downspouts (if not already complete):
- Install gutters along all eaves
- Install downspouts
- Slope gutters toward downspouts (1/4" per 10 feet)
- Extend downspouts 4-6 feet from foundation
- Install leaf guards if desired
Driveway and walks:
- Final grading around all walks
- Seal concrete (if applicable)
- Install driveway markers if needed
- Ensure proper drainage away from house
Days 13-14: Punch List Completion
Systematic room-by-room review:
- Create detailed punch list (if not already done)
- Work through list systematically
- Focus on one room at a time for satisfaction
- Check off completed items
Common punch list items:
Paint touch-ups:
- Touch up all nail holes, dings, scrapes
- Touch up areas damaged during fixture installation
- Touch up caulk lines if needed
Drywall repairs:
- Fix any dents or damage
- Sand and repaint
Trim adjustments:
- Fill any gaps at joints
- Touch up stain or paint
- Adjust doors that don't close properly
- Plane doors that stick
Cleaning:
- Remove all construction debris
- Vacuum all floors and carpets
- Clean all windows inside and out
- Clean all fixtures
- Remove stickers and labels
- Wipe down all cabinets
- Clean appliances
Caulking:
- Touch up any gaps at trim
- Ensure all wet areas properly sealed (tubs, showers, sinks)
- Smooth any rough caulk lines
Hardware check:
- Ensure all screws tight
- Verify all hardware functions properly
- Tighten loose doorknobs
- Adjust cabinet doors/drawers
Floor protection removal:
- Remove protective coverings
- Clean floors thoroughly
- Repair any damage
Final Day: Pre-Inspection Walk-Through
Prepare for final inspection:
-
Complete entire punch list
-
Clean house thoroughly
-
Ensure all utilities operational
-
Test all systems:
- All lights work
- All outlets work (use outlet tester)
- All plumbing fixtures work, no leaks
- HVAC operates properly
- All appliances functional
- All smoke/CO detectors work
- Garage door safety sensors work
-
Verify code compliance items:
- House numbers visible
- Smoke detectors in all required locations
- CO detectors if gas appliances
- Handrails on stairs secure
- GFCI outlets test properly
- Tamper-resistant outlets in required locations
-
Have documentation ready:
- Building permit
- All inspection records
- Product manuals and warranties
- Paint color records
- As-built drawings (if available)
Code Requirements for Final Inspection
IRC requirements inspectors check:
- IRC R314 - Smoke alarms: Proper locations, interconnected, functional
- IRC R315 - Carbon monoxide alarms: Required if fossil fuel appliances or attached garage
- IRC R311.7.8 - Handrails: Secure, proper height (34-38"), graspable
- IRC R310 - Emergency escape: Bedroom egress windows operational
- IRC E3901.11 - GFCI testing: All GFCI outlets functional
- IRC E3901.12 - AFCI testing: All AFCI breakers functional
- IRC R309.5 - Garage separation: Fire-rated door, self-closing
- IRC M1502.4 - Dryer exhaust: Terminates outside, proper material
Common final inspection failures:
- Missing or non-functional smoke detectors
- Garage door opener safety sensors not working
- GFCI outlets not functioning
- Handrails not secure
- Missing house numbers
- Incomplete punch list items (inspector may note but not fail)
Final Inspection Process
What to expect:
- Inspector conducts walk-through (45-90 minutes typical)
- Tests safety items (smoke detectors, GFCI, CO detectors)
- Verifies all systems operational
- Checks for code compliance
- Provides inspection report
If you pass:
- Receive Certificate of Occupancy (CO)
- Can legally occupy the house
- Can close construction loan and convert to permanent mortgage
- Celebration time!
If you fail:
- Receive list of deficiencies
- Correct all items
- Schedule re-inspection
- Typical re-inspection within 3-7 days
Be present for final inspection. Answer inspector's questions. Take notes on any items they mention. Most inspectors are helpful and will explain what they're looking for.
Subcontractor Considerations
Most final finishes are easy DIY tasks. Consider hiring for:
Appliance installation:
- Gas range hookup: $100-$200 (must be licensed)
- Dishwasher install: $150-$300
- Washer/dryer install: $100-$200
Complex fixtures:
- Chandelier installation (very heavy): $100-$250
- Ceiling fan installation: $75-$150 per fan
Garage door opener: $200-$400 installed
Typical DIY savings: $1,500-$3,000 by installing most fixtures yourself
Common Mistakes
1. Rushing Final Inspection
Why it's a problem: Fail inspection, delays occupancy, stress. How to avoid: Complete thorough punch list before calling for inspection. Cost if you don't: Re-inspection fees, delayed move-in, carrying costs.
2. Missing Smoke Detector Locations
Why it's a problem: Code violation, failed inspection, safety hazard. How to avoid: One in each bedroom, one outside each sleeping area, one per floor minimum. Interconnected. Cost if you don't: Failed inspection, $200-$500 to add and wire.
3. Non-Functional GFCI
Why it's a problem: Code violation, safety hazard, failed inspection. How to avoid: Test all GFCI outlets before inspection. Replace any that don't trip. Cost if you don't: Failed inspection, troubleshooting time.
4. Garage Door Sensor Issues
Why it's a problem: Safety hazard, code requirement, failed inspection. How to avoid: Test sensors - door should reverse if beam broken. Adjust if needed. Cost if you don't: Failed inspection, $100-$200 repair.
5. Incomplete Punch List
Why it's a problem: Unfinished appearance, inspector may note items, delays satisfaction. How to avoid: Work through punch list systematically. Don't rush. Cost if you don't: Items get forgotten, must fix later at higher cost.
6. No House Numbers
Why it's a problem: Code requirement in most jurisdictions, safety issue (emergency services). How to avoid: Install clearly visible numbers (4"+ tall, contrasting color). Cost if you don't: Failed inspection or inspector note.
7. Forgetting Product Manuals
Why it's a problem: Can't operate systems, troubleshooting difficult, warranty issues. How to avoid: Collect all manuals in binder. Create list of model numbers. Cost if you don't: Difficulty using systems, warranty claims harder.
8. Poor Cleaning
Why it's a problem: Construction dust everywhere, HVAC contamination, poor first impression. How to avoid: Thorough cleaning before final inspection. Consider professional post-construction cleaning. Cost if you don't: Hours of cleaning yourself, HVAC filter replacement.
Quality Checkpoints
Before final inspection:
- [ ] All light fixtures installed and operational
- [ ] All outlet and switch covers installed
- [ ] Smoke detectors in all required locations, tested
- [ ] CO detectors if required, tested
- [ ] All plumbing fixtures complete, no leaks
- [ ] All appliances installed and operational
- [ ] All door hardware installed, doors operate smoothly
- [ ] All cabinet hardware installed
- [ ] House numbers installed and visible
- [ ] Garage door opener functional with safety sensors
- [ ] All GFCI outlets tested and functional
- [ ] All punch list items complete
- [ ] Paint touch-ups complete
- [ ] House thoroughly cleaned
- [ ] All systems tested and operational
- [ ] All documentation organized
- [ ] Ready for final inspection
Budget Breakdown
Example for 2,000 sq ft house:
| Item | Cost | Notes |
|---|---|---|
| **Fixtures and Hardware** | ||
| Light fixtures (25 units) | $1,000-$3,000 | Mix of styles |
| Outlet/switch covers (75) | $75-$225 | Standard white |
| Smoke/CO detectors | $150-$400 | Hardwired, interconnected |
| Door hardware (15 doors) | $450-$1,200 | Knobs and deadbolts |
| Cabinet hardware | $200-$600 | Included in cabinets or separate |
| Towel bars, TP holders | $150-$400 | All bathrooms |
| **Appliances** | ||
| Refrigerator | $800-$3,000 | Included in kitchen budget |
| Dishwasher | Included | In kitchen budget |
| Range | Included | In kitchen budget |
| Microwave | Included | In kitchen budget |
| Washer/Dryer | $1,000-$2,500 | Separate purchase |
| **Exterior** | ||
| House numbers | $20-$80 | Visible from street |
| Mailbox | $50-$200 | Per USPS requirements |
| Doorbell | $50-$300 | Basic to video |
| **Misc** | ||
| Garage door opener | $200-$500 | With installation |
| Window treatments | $500-$2,000 | Basic coverage |
| Cleaning supplies | $100-$200 | Final cleaning |
| **Labor (if hiring any)** | $500-$2,000 | Selective tasks |
| **Total** | **$5,245-$16,705** | Wide range based on selections |
Timeline Tips
Scheduling:
- Work systematically room by room
- Complete punch list before scheduling final inspection
- Allow 2-3 days for unexpected items
- Schedule final inspection when confident everything is complete
Prioritization:
- Safety items first (smoke detectors, GFCI, safety sensors)
- Required items second (code requirements)
- Functional items third (make house livable)
- Aesthetic items last (nice-to-have)
What Comes Next
After final inspection passes:
- Receive Certificate of Occupancy
- Close construction loan / convert to mortgage
- Final landscaping (often done before CO but not required)
- Move in!
- Enjoy your new home
Link to: Landscaping Phase
Related Resources
Need Final Finishes Help?
Final finishes involve many small tasks. If you need help organizing your punch list or ensuring you're ready for final inspection, a consultation can help.