Construction Timeline: Plan Your Build Schedule

Overview

A realistic timeline keeps your project on track, helps you coordinate subcontractors, and lets you plan your life around the build. Most first-time owner-builders underestimate timelines by 30-50%. This guide helps you avoid that mistake.

When This Step Happens

Typical Owner-Builder Timelines

Three Timeline Scenarios

1. Aggressive (Experienced, Full-Time, Few Delays)

2. Typical (Part-Time, Some Experience, Normal Delays)

3. Conservative (Part-Time, First Build, Learning)

For planning purposes, assume Typical scenario and hope for better

Phase-by-Phase Timeline

Pre-Construction (Before Breaking Ground)

Months 1-3: Planning Phase

Months 4-6: Permit Phase

Total pre-construction: 6 months (range: 3-9 months)

Construction Phase Timeline

Phase 1: Site Preparation (2-4 weeks)

Phase 2: Foundation (2-3 weeks)

Phase 3: Framing (3-6 weeks)

Phase 4: Roofing (1-2 weeks)

Phase 5: Rough-Ins (4-6 weeks)

Phase 6: Insulation (3-5 days)

Phase 7: Drywall (2-3 weeks)

Phase 8: Interior Trim (2-3 weeks)

Phase 9: Flooring (1-3 weeks)

Phase 10: Kitchen & Bathrooms (2-4 weeks)

Phase 11: Painting (1-2 weeks)

Phase 12: Final Finishes (1-2 weeks)

Phase 13: CO and Move-In (1 week)

Total construction time: 24-40 weeks (6-10 months)

Critical Path Understanding

What Is Critical Path?

The sequence of tasks that must be completed in order—any delay in these delays the entire project.

Critical path for house construction:

  1. Site prep → Foundation → Framing → Roof → Rough-ins → Insulation → Drywall → Finishes

These cannot be skipped or overlapped

What CAN Overlap

Parallel work opportunities:

The key: Coordination and communication

Common Timeline Killers

1. Weather Delays

Expected impact: 2-4 weeks over full project

Vulnerable phases:

Mitigation:

2. Permit and Inspection Delays

Expected impact: 2-4 weeks over full project

Common issues:

Mitigation:

3. Material Delivery Delays

Expected impact: 2-6 weeks over full project

Long-lead items:

Mitigation:

4. Subcontractor Scheduling

Expected impact: 2-4 weeks over full project

Common issues:

Mitigation:

5. DIY Takes Longer Than Expected

Expected impact: 30-50% longer than estimated

Reality check:

Mitigation:

6. Scope Creep and Changes

Expected impact: 1-3 months over full project

How it happens:

Mitigation:

Creating Your Timeline

Step 1: Use Standard Phase Durations

Start with typical times:

Step 2: Account for Your Situation

Add time if:

Subtract time if:

Step 3: Add Buffer Time

Build in delays:

Total buffer: 8-14 weeks (2-3 months)

Step 4: Create Month-by-Month Schedule

Example timeline (12-month construction):

Month 1: Site prep, foundation Month 2: Framing, roof Month 3: Windows, rough-in plumbing and electrical Month 4: HVAC, insulation, start drywall Month 5: Complete drywall, start interior trim Month 6: Complete trim, start flooring Month 7: Complete flooring, install cabinets Month 8: Countertops, tile work Month 9: Paint entire interior Month 10: Final finishes, light fixtures, hardware Month 11: Bathroom and kitchen final details, landscaping Month 12: Final inspection, punch list, CO, move in

Step 5: Create Rolling 4-Week Detailed Schedule

Each month, plan in detail:

Week 1:

Week 2-4: Similar detail

Update weekly based on progress

Tools for Timeline Management

Simple Tools (Good for Most)

Spreadsheet timeline:

Calendar-based:

Professional Tools (If You Want Them)

Gantt chart software:

Construction-specific:

Most owner-builders don't need this—spreadsheet works fine

Quality Checkpoints

Before starting construction:

Timeline Completeness:

Timeline Realism:

Timeline Feasibility:

Sample Timelines

Example 1: Full-Time Owner-Builder (8 months)

Pre-construction: 3 months Construction:

Total: 11 months

Example 2: Part-Time Owner-Builder (14 months)

Pre-construction: 6 months Construction:

Total: 20 months

Example 3: Weekends Only (24 months)

Pre-construction: 6 months Construction:

Total: 30 months (2.5 years)

What Comes Next

After timeline is created:

Typical gap between timeline creation and construction start: 2-4 weeks

Link to: Site Preparation

Related Resources

Need help coordinating subcontractors? Our subcontractor management guide covers scheduling and communication.

Ready to start building? Begin with our site preparation guide.