Build Timeline Estimator

Get a realistic estimate of how long your owner-builder project will take from permit to move-in. This calculator factors in your available time, experience level, DIY percentage, and provides a phase-by-phase breakdown so you can plan your life accordingly.

Timeline Estimator

Estimate how long your DIY home build will take based on your schedule and experience

Your Project Details

Include evenings, weekends, and vacation time
How much will you do yourself vs. hiring out?
Friends/family who will consistently help

Understanding Build Timelines

Realistic Expectations

Professional builders typically complete a home in 4-6 months. Owner-builders should plan for 12-24 months depending on their schedule and DIY percentage. This isn't failure - it's reality when you're learning while building.

Key insight: Most owner-builders underestimate timelines by 30-50%. It always takes longer than you think, especially when working evenings and weekends.

Hours Per Week Matter

If you can dedicate 20 hours per week (two full days), you're working at 50% of a full-time pace. At 10 hours per week, everything takes twice as long. Weather, life events, and burnout further reduce effective hours.

Reality check: Few owner-builders maintain their planned pace for the entire project. Plan for 60-70% of your estimated hours.

Experience Level Impact

Beginners should add 30-40% to timelines. You'll spend time learning, making mistakes, and doing things twice. Intermediate builders with some construction experience can work at near-professional pace on familiar tasks.

The upside: Skills compound. You'll be much faster at the end than the beginning. Consider doing finish work yourself after hiring out early framing.

Subcontractor Delays

Even when hiring out 50% of work, you'll face scheduling delays. Good subs are busy and may have 2-4 week lead times. Weather delays, failed inspections, and material shortages add weeks to the schedule.

Pro tip: Book subcontractors 4-6 weeks in advance. Get on their schedule early, confirm the week before, and have backup plans.

Critical Path Items

Some tasks must happen in sequence: foundation before framing, framing before roofing, rough-ins before drywall. You can't compress these. Focus your DIY efforts on parallel tasks (site cleanup, painting, trim) that don't hold up critical work.

Strategy: Hire out critical path items (foundation, framing, roofing) to maintain momentum. Do finish work yourself when you have more flexibility.

Seasonal Factors

Building through winter adds 2-4 weeks in most climates. Concrete won't cure below freezing, subs won't work in heavy rain, and you'll hate framing in snow. Plan weatherproof work (interior finishes) for winter months.

Best timeline: Start in spring, get dried-in by fall, finish interior through winter. This minimizes weather delays.

Phase-by-Phase Realities

Here's what actually happens during each phase, based on owner-builder projects:

Planning & Permitting

15% of timeline. Finalizing plans, applying for permits, ordering materials, setting up accounts. Permit approval alone takes 4-12 weeks in most jurisdictions. Start this early while still in feasibility.

Foundation

12% of timeline. Excavation, footings, foundation walls, waterproofing, backfill. Weather dependent. Most owner-builders hire this out entirely. Budget 2-4 weeks for a simple slab, 4-6 weeks for a full basement.

Framing

20% of timeline. Floor system, wall framing, roof framing, sheathing, windows/doors. This is the most exciting phase but requires the most skill. Professional crews take 2-4 weeks. DIY crews: 6-12 weeks.

Rough-Ins

18% of timeline. Electrical, plumbing, HVAC rough-in work. Most owner-builders hire licensed subs for this. Scheduling three different trades takes coordination. Budget 3-6 weeks plus inspection time.

Insulation & Drywall

12% of timeline. Insulation, drywall hanging, taping, mudding, sanding. Many owner-builders do their own insulation but hire drywall. Good drywall finishing takes skill. Budget 2-4 weeks for a typical home.

Interior Finishes

15% of timeline. Trim, doors, cabinets, flooring, painting, countertops. This is where owner-builders can save the most money doing it themselves. Plan for this to take longer than expected - details matter.

Final & Exterior

8% of timeline. Exterior finishes, landscaping, final inspections, punch list items. The last 10% takes as long as you think the last 50% will take. Budget extra time for the endless punch list.

Timeline Management Strategies

Here's how to keep your project on track:

Build Your Schedule Backwards

Start with your move-in date and work backwards. Add 30% buffer time. If you absolutely must be in by next fall, you need to start foundation work this spring - not summer.

Track Actual vs. Estimated

After each phase, compare actual time to estimated. If framing took 50% longer than planned, adjust all remaining estimates up. Don't keep assuming you'll "make up time later."

Protect Your Momentum

The biggest timeline killer is stopping. Once you lose momentum (vacation, work project, illness), it's hard to restart. Try to maintain at least minimal weekly progress even during busy periods.

Book Subs Early

Get on subcontractor schedules 4-6 weeks in advance. Confirm weekly. Have backup subs identified. A single sub delay can cascade into months of lost time.

Batch Similar Tasks

Do all framing at once, all electrical at once, all painting at once. Switching between tasks costs time in setup, cleanup, and mental context switching. Batching is more efficient.

Plan for Life

You'll have work demands, family obligations, holidays, and burnout. Build these into your timeline. A sustainable pace beats heroic sprints followed by multi-week breaks.

Next Steps

Now that you understand the timeline, explore other planning tools.