Managing Subcontractors: Day-to-Day Success
Hiring quality subcontractors is half the battle. Managing them effectively is the other half. Good management keeps your project on schedule, ensures quality work, maintains positive relationships, and prevents most problems before they happen.
This guide covers the day-to-day practices that separate successful owner-builder projects from problem projects: scheduling, communication, site management, quality control, and maintaining positive working relationships.
Your Role as Owner-Builder GC
As your own general contractor, you're responsible for:
Before Work Starts
- Scheduling and sequencing all trades
- Ensuring site is ready for each sub
- Ordering and delivering materials (if owner-provided)
- Coordinating permits and inspections
- Setting clear expectations
During the Work
- Being available and responsive
- Monitoring quality and progress
- Identifying and solving problems quickly
- Documenting everything with photos
- Coordinating between trades
- Managing the schedule
- Maintaining site safety and cleanliness
After Work Completes
- Inspecting work before payment
- Managing punch lists
- Getting inspections passed
- Processing payments promptly
- Maintaining relationships for callbacks
Time commitment: 10-20 hours per week during active construction
This is a real job. Treat it professionally or your project will suffer.
Scheduling and Sequencing
The challenge: Coordinating multiple trades in the correct sequence without delays.
Standard Build Sequence
Foundation to finish:
- Site work and excavation
- Foundation
- Underground plumbing/utilities
- Foundation backfill
- Framing
- Windows and exterior doors
- Roofing
- Exterior siding/finish
- Rough plumbing
- Rough electrical
- Rough HVAC
- Insulation
- Drywall
- Interior trim
- Cabinets
- Flooring
- Plumbing fixtures
- Electrical fixtures
- HVAC final
- Paint touch-up
- Final cleaning
- Landscaping
Key principle: Can't skip ahead. Each phase must complete before next begins.
Creating Your Schedule
Master schedule approach:
Start with completion date, work backwards:
- Completion: December 1
- Final work (4 weeks): November 1-30
- Interior finish (6 weeks): September 15-October 31
- Drywall/paint (4 weeks): August 15-September 14
- Rough-ins (6 weeks): July 1-August 14
- Framing (8 weeks): May 1-June 30
- Foundation (3 weeks): April 8-28
- Site work (2 weeks): March 25-April 7
- Start date needed: March 25
Add buffer (20-30%):
- Things always take longer
- Weather delays
- Material delays
- Failed inspections
- Subcontractor delays
Result: Start date should be March 1 to finish December 1
Booking Subcontractors
Timeline:
- Book critical-path subs 3-4 months ahead
- Book long-lead subs first (framing, HVAC, cabinets)
- Book others 2-3 months ahead
- Have backup subs identified
Give them:
- Tentative start date (will confirm 2 weeks prior)
- Expected duration
- Rough schedule position
- Who comes before/after them
Get from them:
- Commitment to timeline
- Lead time needed for materials
- How much notice they need to start
- Any schedule conflicts
Example communication:
"I'll need you for framing starting approximately June 1st. I'll confirm the exact start date by May 15th. The rough-in trades are scheduled to start July 1st, so we need framing complete by June 28th. Can you commit to this timeline?"
Coordination Between Trades
The problem: Trade A isn't done, but Trade B is scheduled to start.
The solution: Clear communication and buffer time.
Best practices:
-
Give 2-week notice before start
- Confirms sub is still available
- Allows them to schedule crew
- Updates them on actual schedule
- Prevents surprises
-
Don't schedule back-to-back
- Allow 3-5 days between trades
- Buffer for delays, inspections, weather
- Prevents one delay cascading
-
Confirm completion before booking next
- Verify Trade A is done before starting Trade B
- Don't book based on hopes and promises
- Better to delay than have subs waiting
-
Have backup plans
- Secondary subs on standby
- Flexible dates when possible
- Work that can be done in parallel
Example schedule with buffers:
- Framing: June 1-28 (4 weeks)
- Buffer: June 29-July 3 (5 days for inspection, weather, delays)
- Rough plumbing: July 6-12 (1 week)
- Rough electrical: July 13-19 (1 week)
- Rough HVAC: July 20-26 (1 week)
- Buffer: July 27-31 (5 days for inspections)
- Insulation: August 3-7 (1 week)
When Things Get Off Schedule
They will. Here's how to handle it:
If one trade runs late:
- Contact next trade immediately
- Give them updated start date
- Confirm they can still do the work
- If not, activate backup plan
- Adjust rest of schedule
If weather delays you:
- Update all affected subs
- Push everything back proportionally
- Don't try to compress later work (quality suffers)
- Add buffer for additional weather risk
If inspection fails:
- Fix issues IMMEDIATELY
- Call for re-inspection ASAP
- Notify next trade of delay (usually 3-7 days)
- Don't let next trade start until inspection passes
If materials are delayed:
- Know about it early (track shipments)
- Notify sub immediately
- Reschedule if significant delay
- Find alternative suppliers if critical
Communication Best Practices
Good communication prevents 90% of problems.
How to Communicate
Methods (use all three):
-
Text/SMS - Best for quick updates
- "Inspection passed, you're good to start Monday"
- "Running 30 minutes late"
- "Quick question about..."
-
Phone calls - Best for complex discussions
- Scheduling changes
- Problem-solving
- Detailed questions
- Anything emotional or complicated
-
Email - Best for documentation
- Change orders
- Important decisions
- Anything you need record of
- Plans and specifications
Pro tip: Have important discussions by phone, then confirm in email
Example:
- Call: Discuss change to framing plan
- Email: "Per our conversation, you'll use 2x12 instead of 2x10 for $850 additional. Please confirm."
- Text: "Did you see my email about the header change?"
Response Time Expectations
You to them:
- Text: Within 2-4 hours during work day
- Email: Within 24 hours
- Phone: Return calls same day
- Emergencies: Immediately
Them to you (set this expectation):
- Urgent: Within 1-2 hours
- Normal: Same business day
- Questions: Before proceeding with assumptions
Set expectations upfront:
"I'm usually available by text 7 AM-7 PM. I'll respond within a few hours. For urgent issues, call me directly. I need you to check in daily with progress and any issues."
Daily Check-Ins
While sub is working:
- Daily text or call
- "How's it going? Any issues?"
- "Still on track for Friday completion?"
- "Need anything from me?"
Why this works:
- Catch problems early
- Show you're engaged
- Build relationship
- Prevent surprises
Takes 5 minutes per day, saves hours of problems
Site Visits
How often to visit:
- Critical work: Daily
- Important work: Every 2-3 days
- Routine work: 2-3 times per week
- Final walk-through: Before payment
What to do during visits:
- Inspect work quality
- Take photos
- Ask questions
- Check progress against schedule
- Identify potential issues
- Show you care and are paying attention
What NOT to do:
- Micromanage
- Constantly interrupt
- Question every decision
- Bring up non-urgent issues
- Stand over them watching
Balance: Be present but not overbearing
Quality Control
Your responsibility: Ensure work meets code and contract requirements.
Before Work Starts
Pre-work meeting:
- Review scope of work
- Review plans together
- Discuss any questions
- Clarify expectations
- Review inspection requirements
- Confirm materials and specifications
Provide:
- Clean plans marked "FOR CONSTRUCTION"
- Material specifications in writing
- Access to site
- Utilities if needed
- Clear area for material delivery
During the Work
Daily monitoring:
- Visual inspection of work
- Take photos of progress
- Check against plans
- Verify materials being used
- Note any deviations
- Ask questions if unclear
What to look for (even if you're not an expert):
- Does it match the plans?
- Does it look straight/level/square?
- Are they using specified materials?
- Does work look neat and professional?
- Are they creating problems for next trade?
When to speak up:
- Anything doesn't match plans
- Materials are different than specified
- Work looks wrong (even if you don't know why)
- Safety concerns
- Damage to other work
How to address issues:
- Ask questions first: "Can you explain why you're doing it this way?"
- Reference plans: "The plan shows this differently. Can we discuss?"
- Stop work if necessary: "Let me check with [inspector/engineer] before you proceed."
- Document everything: Photos and written notes
Never:
- Assume they know best without questioning
- Let work proceed that seems wrong
- Cover up work you haven't inspected
- Skip inspection to "save time"
Before Inspection
Pre-inspection walk-through:
- You and contractor inspect together
- Review all work
- Check against code requirements
- Verify everything complete
- Fix obvious issues before inspector comes
- Take photos
Checklist approach:
- Create inspection checklist for each trade
- Review item by item
- Don't call inspector until truly ready
- Better to delay than fail
Inspection-specific checklists →
After Inspection
If passed:
- Thank contractor
- Take photos of inspection card
- Authorize next trade to start
- Process payment per contract
If failed:
- Review corrections with contractor
- Set timeline for fixes
- Verify fixes before calling for re-inspection
- Don't pay until re-inspection passes
Site Management
Your property, your responsibility:
Site Access
Provide:
- Clear access for vehicles
- Parking area
- Material delivery area
- Hours of access (typically 7 AM-6 PM weekdays)
Security:
- Lockbox for key access
- Secure site at end of day
- Remove valuable tools/materials
- Liability for theft on contractors
Set rules:
- No weekend/evening work without approval
- No smoking on site
- No alcohol/drugs (zero tolerance)
- No unauthorized personnel
- Bathroom facilities (porta-potty)
Safety
Contractor responsibilities:
- OSHA compliance
- Safety equipment for their workers
- Safe work practices
- Cleanup of hazards
Your responsibilities:
- Safe site conditions
- No exposure to hazardous materials without proper disclosure
- Adequate lighting
- Safe access
Watch for:
- Unsafe ladder use
- No fall protection at heights
- Electrical hazards
- Tripping hazards
- Unsafe material storage
If you see unsafe practices:
- Address immediately
- You're liable for injuries on your property
- Stop work if necessary
- Document with photos
Cleanliness and Organization
Daily cleanup expectations:
- Work area swept/cleaned
- Scrap materials in dumpster
- Tools organized
- Pathways clear
- Hazards eliminated
Weekly cleanup:
- More thorough site cleaning
- Organize material piles
- Maintain dumpster
- Remove trash
Final cleanup:
- Broom-clean condition
- All debris removed
- Protect finished surfaces
- Ready for next trade
Include in contract: Daily cleanup requirements
Protecting Completed Work
Contractor responsibilities:
- Don't damage other trades' work
- Protect what they install
- Repair damage they cause
Your responsibilities:
- Provide protection materials if needed
- Coordinate trades to minimize damage
- Document condition before/after each trade
Common issues:
- Drywall damaged moving materials
- Floors scratched/gouged
- Fixtures damaged
- Painted surfaces marked/chipped
Prevention:
- Floor protection (Masonite, cardboard, Ram Board)
- Corner guards on drywall
- Cover finished fixtures
- Clear communication about protection
Documentation
Document everything. Seriously.
What to Photograph
Before work starts:
- Site conditions
- Existing work
- What contractor will build on
During work:
- Daily progress
- All work before it's covered
- Any issues or concerns
- Materials being used
- How work is being done
After work completes:
- Finished work from multiple angles
- Inspection cards/approvals
- Any punch-list items
- Final condition
Why photos matter:
- Prove work was done correctly
- Document what's behind walls
- Support insurance claims
- Resolve disputes
- Reference for future work
How to organize:
- By trade
- By date
- By location
- Cloud storage (Google Photos, Dropbox)
- Backup everything
What to Document in Writing
Keep records of:
- All contracts and change orders
- Payment records (checks, invoices)
- Inspection reports
- Lien releases
- Insurance certificates
- Licenses
- Daily logs (who was on site, what was done)
- Weather delays
- All communications about important decisions
Daily log example:
Date: June 15, 2024
Trade: Framing
Workers present: 4
Work completed: First floor walls framed, stood, braced
Weather: Sunny, 75°F
Issues: None
Notes: On schedule, quality looks good
Photos: 24 taken, uploaded to folder
Next: Second floor walls tomorrow
Takes 5 minutes per day, invaluable for disputes/insurance/reference
Managing Multiple Subs at Once
The challenge: Coordinating when multiple trades are on site simultaneously.
When this happens:
- Rough-in phase (plumbing, electrical, HVAC)
- Finish phase (multiple finish trades)
- Exterior work (siding, trim, painting may overlap)
Coordination strategies:
1. Daily Coordination Meeting
When: Each morning, 15 minutes Who: All trades on site that day Topics:
- Who's working where today
- Potential conflicts
- Shared resources (power, ladders, etc.)
- Schedule for the day
- Any safety issues
Example:
"Electricians working upstairs. Plumbers working basement. HVAC delivery at 10 AM, everyone help unload. Everyone off second floor during HVAC delivery. Questions?"
2. Designate Site Lead
Who: Most senior contractor or you Role: Resolves conflicts, makes decisions, coordinates Authority: Can pause work if conflicts arise
3. Stagger Start Times
Instead of: Everyone arrives 7 AM Better:
- Trade A: 7 AM-3 PM
- Trade B: 8:30 AM-4:30 PM
- Trade C: 9 AM-5 PM
Reduces: Parking conflicts, bathroom line, crowding
4. Zone the Site
Assign areas:
- Plumber: Basement and first floor
- Electrician: Second floor and attic
- HVAC: First floor only
Rotate as work completes
Prevents: Getting in each other's way
Building Good Relationships
Good relationships = Better work + Fewer problems + Priority scheduling
What Contractors Appreciate
-
Clear communication
- Tell them what you want
- Respond promptly
- Be available when needed
-
Respect their time
- Don't waste time with indecision
- Have answers ready when they ask questions
- Make decisions promptly
-
Respect their expertise
- Listen to their suggestions
- Don't micromanage
- Ask questions, don't dictate (usually)
-
Fair treatment
- Pay on time as agreed
- Don't nickel-and-dime
- Acknowledge good work
- Be reasonable with requests
-
Being prepared
- Site ready when they arrive
- Materials available
- Plans and decisions finalized
- Access arranged
-
Professional attitude
- Keep emotions in check
- Address issues calmly
- Follow the contract
- Be solution-focused
What Annoys Contractors
Avoid these behaviors:
-
Constant changes
- Changing mind repeatedly
- Making decisions after work starts
- "While you're here, can you also..."
-
Micromanaging
- Standing over them watching
- Questioning every decision
- Telling them how to do their job
-
Poor communication
- Not returning calls
- Unclear expectations
- Contradictory instructions
-
Late payments
- Delaying payment without reason
- Nitpicking to avoid paying
- "I'll pay you when I have money"
-
Unrealistic expectations
- Demanding impossible timelines
- Expecting perfection beyond code
- Comparing to TV shows
-
Being unprepared
- Site not ready
- Materials not ordered
- No decisions made
- Wasting their time
The Golden Rule
Treat contractors like you'd want to be treated in your own profession.
Professional, respectful, clear, fair.
Result: They'll prioritize your work, do quality job, stand behind it, and refer you to other quality trades.
Common Management Mistakes
1. Not Being Available
The mistake: Too busy to respond, hard to reach
Impact: Delays while they wait for answers, frustration, poor decisions made without your input
Fix: Block time daily for project management, respond promptly
2. Over-Managing
The mistake: Constantly on site, questioning everything
Impact: Slows work, irritates contractors, they avoid you
Fix: Visit regularly but let them work, ask questions but don't interrogate
3. Poor Documentation
The mistake: No photos, no records, verbal agreements only
Impact: No evidence for disputes, can't remember what's behind walls, insurance issues
Fix: Daily photos, written logs, document all decisions
4. Not Enforcing Contract
The mistake: Letting contract terms slide to be "nice"
Impact: Sets bad precedent, lose leverage, problems escalate
Fix: Follow contract terms consistently, be fair but firm
5. Delaying Decisions
The mistake: "I'll think about it and get back to you" repeatedly
Impact: Work stops, schedule delays, contractors frustrated
Fix: Make decisions promptly or give clear timeline for decision
6. Ignoring Small Issues
The mistake: Letting small problems slide to avoid conflict
Impact: Small issues become big problems, hard to address later
Fix: Address issues immediately but professionally
7. Paying Too Fast
The mistake: Paying before inspection or verification
Impact: No leverage for corrections, quality may suffer
Fix: Verify work complete and correct before paying
8. No Inspection Before Payment
The mistake: Paying based on contractor saying "it's done"
Impact: Miss quality issues, defects, incomplete work
Fix: Always inspect personally before paying
Management Checklist
Weekly management tasks:
- [ ] Reviewed schedule, confirmed with all upcoming subs
- [ ] Visited site 2-3 times minimum
- [ ] Took photos of all progress
- [ ] Checked in daily with active subs
- [ ] Addressed any issues that arose
- [ ] Verified work quality
- [ ] Processed any payments due
- [ ] Planned next week's work
- [ ] Ordered any materials needed
- [ ] Updated project log
- [ ] Backed up all photos/documents
Next Steps
Managing subcontractors also requires understanding:
-
Payment Best Practices → - When and how to pay for maximum protection
-
Dealing with Problems → - What to do when things go wrong
-
Inspections → - Managing the inspection process
**The bottom line