Payment Schedules and Best Practices
How and when you pay subcontractors is one of your most powerful management tools as an owner-builder. Payment done right protects you legally, maintains quality leverage, and ensures project completion. Payment done wrong leaves you exposed to liens, abandoned work, and poor quality.
This guide will teach you industry-standard payment practices, how to protect yourself at every payment stage, when to hold payment, and how to handle payment disputes professionally.
Why Payment Strategy Matters
The leverage principle: Whoever holds the money has the power.
Pay too much upfront: Contractor has your money, you have no leverage Pay too little: Contractor can't afford materials, may abandon job Pay correctly: Contractor is motivated to complete quality work, you're protected
Real examples:
Bad payment: Paid 60% upfront ($18,000 of $30,000 contract)
- Contractor worked 2 weeks, disappeared
- Work was 40% complete
- Owner out $18,000 with half-finished work
- Cost $15,000 to hire new contractor to complete
- Total loss: $33,000 to complete $30,000 job
Good payment: Paid 15% deposit, then progress-based payments
- Contractor worked steadily
- Owner inspected before each payment
- Quality maintained throughout
- Final 15% held until truly complete
- Work finished on time, on budget
The difference: Payment structure
Standard Payment Structures
Industry Standard (Recommended)
Four-payment structure:
- Deposit: 10-20% at contract signing
- Progress 1: 30-35% at defined milestone
- Progress 2: 30-35% at next milestone
- Final: 15-20% at completion + lien release
Example for $20,000 contract:
- Deposit: $3,000 (15%) - At signing
- Progress 1: $7,000 (35%) - At 50% completion milestone
- Progress 2: $7,000 (35%) - At substantial completion
- Final: $3,000 (15%) - After lien release + punch list
Why this works:
- Small deposit shows commitment without high risk
- Progress payments keep contractor liquid
- You always owe less than work completed
- Final payment ensures completion and lien protection
- Contractor stays motivated throughout
Three-Payment Structure (Simpler)
For smaller projects (under $10,000):
- Deposit: 10-20%
- Mid-point: 40-50%
- Final: 30-40%
Example for $8,000 contract:
- Deposit: $1,200 (15%)
- Mid-point: $4,000 (50%)
- Final: $2,800 (35%)
Trade-Specific Payment Schedules
Different trades have different natural payment breakpoints:
Foundation/Concrete
Deposit: 15% - At contract signing
Payment 1: 35% - After footings poured and inspected
Payment 2: 35% - After walls poured and inspected
Final: 15% - After backfill complete and final inspection
Framing
Deposit: 15% - At contract signing
Payment 1: 30% - First floor framed and sheathed
Payment 2: 30% - Second floor and roof framed
Payment 3: 10% - Sheathing and house wrap complete
Final: 15% - After inspection passed and punch list complete
Roofing
Deposit: 15% - At contract signing (if materials included)
Payment 1: 50% - Underlayment and shingles installed
Final: 35% - Ridge cap, flashing complete, cleanup done
Plumbing/Electrical/HVAC
Deposit: 10% - At contract signing
Rough-in: 45% - After rough-in complete and inspected
Finish: 30% - After fixtures/devices installed
Final: 15% - After final inspection and punch list
Drywall
Deposit: 10% - At contract signing
Hanging: 25% - After all drywall hung
Taping/First coat: 25% - After first coat of mud
Finish: 25% - After sanding and priming
Final: 15% - After touch-ups and cleanup
Payment Milestones
Key principle: Payments tied to measurable completion, not time elapsed.
Good Milestones (Measurable)
- "Footings poured and inspected"
- "Rough plumbing complete and inspection passed"
- "All drywall hung"
- "Substantial completion per contract scope"
Bad Milestones (Vague)
- "After 2 weeks"
- "When about half done"
- "When contractor requests payment"
- "Mid-project"
How to Define Milestones
Be specific:
PAYMENT MILESTONE 1: $7,000 due when:
☑ All first-floor walls framed per plan
☑ All second-floor walls framed per plan
☑ All exterior walls sheathed with 7/16" OSB
☑ House wrap installed on all exterior walls
☑ Work photographed and verified by owner
☑ Site cleaned of debris
Owner shall inspect within 3 business days and payment due within
5 business days of verification.
Not this:
"$7,000 when framing is halfway done"
Deposit Guidelines
Deposits serve one purpose: Secure contractor's commitment and cover initial material costs
Standard deposit amounts:
- Materials-intensive trades: 15-20% (roofing, foundation)
- Labor-intensive trades: 10-15% (framing, drywall)
- Never exceed 25% under any circumstances
Red flags:
- 30%+ deposit request: Warning sign
- 50%+ deposit request: Major red flag, likely scam or cash-flow problems
- "Need money for materials before starting": Should be in quote, not extra deposit
- "Need to buy truck/tools/equipment": Not your problem
When contractor asks for large deposit:
Wrong response: Pay it because you want to secure them
Right response:
"I understand you need to cover materials. Standard industry practice is 10-20% deposit. I'm comfortable with 15%. If you need more for materials, let's set up supplier accounts where I pay directly, or I'll provide materials myself. I won't be paying more than 20% before work begins."
If they refuse: Find a different contractor. Financial stability is questionable.
Progress Payment Best Practices
Before Making Any Progress Payment
Required steps:
-
Inspect the work yourself
- Compare to contract scope
- Verify milestone actually achieved
- Check quality
- Take photos
- Note any issues
-
Verify inspections passed (if applicable)
- Get copy of inspection card
- Confirm no corrections needed
- Photos of passed inspection
-
Get conditional lien release
- Contractor signs lien release covering work to date
- Release becomes effective when payment clears
- Protects you from liens for that payment period
-
Verify previous payments used properly
- No liens filed
- Materials on-site that were supposed to be purchased
- Subcontractors paid (if applicable)
-
Document everything
- Photos of completed milestone
- Inspection results
- Lien release
- Invoice from contractor
- Your verification notes
Only after all steps: Issue payment
The Verification Process
Step-by-step:
1. Contractor notifies you milestone reached
- Text/email: "Rough plumbing complete, ready for inspection"
2. You schedule inspection (if required)
- Call building department
- Coordinate with contractor
- Be present for inspection
3. Inspection occurs and passes
- Get copy of inspection card/approval
- Photo the card
- Note any comments from inspector
4. You inspect personally
- Walk through with contractor
- Check against contract scope
- Verify milestone criteria met
- Take comprehensive photos
- Create punch list if minor items
5. Request lien release
- Provide conditional lien release form
- Contractor signs
- You keep original
6. Process payment
- Issue check or transfer
- Include payment number and milestone covered
- Keep records
Timeline: 3-5 business days from verification to payment
This protects you and is fair to contractor
Final Payment Procedures
Final payment is different: Most critical for your protection
Before Final Payment
Must have:
-
100% completion verified
- All contract scope complete
- All punch-list items done
- No outstanding work
- Quality acceptable
-
All inspections passed
- Final inspection if required
- Certificate of occupancy if applicable
- Copies of all inspection records
-
Unconditional lien release
- Contractor provides unconditional release
- Covers all work performed
- Signed and notarized if required
-
Subcontractor lien releases (if contractor used subs)
- Release from every subcontractor
- Proves they've been paid
- Protects you from their liens
-
Warranty documentation
- Written warranty per contract
- Manufacturer warranties assigned to you
- Contact information for warranty service
-
Final cleanup complete
- Site broom-clean
- All debris removed
- All tools/equipment removed
- Protected work areas restored
-
As-built documentation (if applicable)
- Any changes from original plans
- Photos of installed work
- Product specifications
- Maintenance instructions
Never pay final payment without ALL of these
The 30-Day Hold
Additional protection: Hold final 10% for 30 days after completion
Why 30 days:
- Mechanics lien filing deadline (30-90 days in most states)
- Allows time for liens to surface
- Immediate defects become apparent
- Gives you leverage for callbacks
How it works:
Contract total: $20,000
Regular payments: $18,000
Final 10%: $2,000
Completion date: June 15
Hold until: July 15 (30 days)
Payment if no issues: July 15
If lien filed or defect found: Hold until resolved
Include in contract:
"Final 10% of contract price held for 30 days after substantial completion to ensure no liens are filed and no latent defects appear. Payment released after 30 days if no liens filed and no defects discovered."
Contractors who refuse this: May be planning to not pay their subs (red flag)
Lien Releases
Critical protection: Prevents mechanics liens on your property
What is a Mechanic's Lien?
Definition: Legal claim against your property for unpaid construction work
How it happens:
- You pay contractor
- Contractor doesn't pay their suppliers/subs
- Supplier/sub files lien against YOUR property
- You must pay them or they can force sale of property
The problem: You pay twice (contractor and lien claimant)
The solution: Lien releases with every payment
Types of Lien Releases
Conditional Lien Release
Used for: Progress payments Means: "I release lien rights when payment clears"
When to get: With every progress payment Becomes effective: When check clears or transfer completes
Example form:
CONDITIONAL LIEN RELEASE
In exchange for payment of $7,000 from [Owner Name], which payment
has been received/upon receipt, [Contractor Name] releases and waives
all lien rights for labor and materials furnished to [Property Address]
through [Date] to the extent of $7,000.
This release is conditional on payment clearing.
Signature: _________________ Date: _______
Unconditional Lien Release
Used for: Final payment only Means: "I release all lien rights, period"
When to get: Before final payment Becomes effective: Immediately upon signing
Example form:
UNCONDITIONAL LIEN RELEASE
[Contractor Name] has received final payment of $3,000 from [Owner Name]
for all labor and materials furnished to [Property Address].
[Contractor Name] releases and waives all lien rights for all work
performed and materials furnished through the completion of this project.
This release is unconditional and effective immediately.
Signature: _________________ Date: _______
Subcontractor Lien Releases
Required: Lien releases from contractor's subs and suppliers
When contractor uses subs, you need:
- Contractor's lien release
- Every subcontractor's lien release
- Every major supplier's lien release
How to request:
"As a condition of final payment, please provide unconditional lien releases from yourself and all subcontractors and material suppliers who worked on this project. I need releases from [list specific subs you know about] at minimum."
If contractor won't provide:
- Major red flag (likely hasn't paid subs)
- Don't make final payment
- Consider paying subs directly
Lien Release Forms
Where to get:
- State construction lien statute (specifies required format)
- State contractor licensing board
- Attorney
- Title company
- Pre-made forms online (verify they meet state requirements)
State-specific: Forms must comply with your state's lien law
Have ready: Blank forms for contractors to sign at each payment
When to Hold Payment
Sometimes you must withhold payment to protect yourself:
Valid Reasons to Withhold
-
Work incomplete
- Milestone not actually reached
- Scope items missing
- Punch list not done
-
Work defective
- Doesn't meet code
- Failed inspection
- Poor quality not per contract
-
No lien release
- Contractor won't provide
- Concern about unpaid subs
-
Missing documentation
- No inspection approval
- No warranty documents
- No as-built information
-
Damage to property
- Contractor damaged other work
- Damage not yet repaired
-
Breach of contract
- Violated contract terms
- Missed deadlines with liquidated damages
- Used wrong materials
How to Withhold Payment Properly
Do it right or you're in breach:
Step 1: Document the issue
- Photos
- Written description
- Reference to contract violation
- Cost to remedy if quantifiable
Step 2: Notify contractor in writing
[Date]
[Contractor Name],
I am withholding payment of $[Amount] due [Date] for the following
reasons:
1. [Specific issue with contract reference]
2. [Specific issue with contract reference]
To release payment, please:
- [Specific action required]
- [Specific action required]
I'm happy to discuss these issues and work toward resolution.
[Your Name]
Step 3: Give reasonable time to cure
- 7-10 days for minor issues
- 30 days for major corrections
- Timeline should match contract
Step 4: Re-inspect and pay when resolved
- Verify corrections made
- Process payment promptly
- Document resolution
What NOT to do:
- Withhold without specific reason
- Refuse payment to negotiate price down
- Hold payment for non-contract items
- Use payment as punishment
The line: You can withhold for legitimate contract breaches, not to be difficult
Payment Timing
How quickly should you pay after verification?
Standard: 5-7 business days from verification
Reasonable: 10 business days
Slow: 14+ business days (will frustrate contractors)
Unreasonable: 30+ days (breach of contract typically)
Best practice: Pay within 5 business days
- Shows professionalism
- Builds goodwill
- Encourages continued quality
- Prevents cash flow issues for contractor
Exceptions: Legitimate issues that require withholding (see above)
Payment Methods
Recommended: Check
Pros:
- Clear paper trail
- Memo line for documentation
- Takes 3-5 days to clear (gives you protection)
- Professional
- Legal documentation
Best practice:
- Mail or hand-deliver
- Memo line: "Payment 2 of 4 - Rough Plumbing per contract dated X"
- Photograph check before sending
- Get signature if hand-delivering
Also Good: ACH/Bank Transfer
Pros:
- Fast, efficient
- Digital record
- No check writing
Cons:
- Immediate (less protection window)
- Requires sharing bank info
Acceptable: Credit Card (Rarely Used)
Pros:
- Chargeback protection
- Rewards points
- Clear record
Cons:
- Contractor pays 2-3% fee
- May refuse or add fee to price
Never: Cash
Why not:
- No documentation
- Can't prove payment
- Tax issues
- No protection
- No lien release leverage
- Unprofessional
If contractor insists on cash: Major red flag, find different contractor
Late Payment Penalties (If You're Late)
Some contractors include late payment terms:
- 1-1.5% per month interest on late payments
- $50-100 flat fee after X days
Are these enforceable? Usually yes, if in contract
How to avoid:
- Pay on time per contract
- If you'll be late, communicate early
- Negotiate payment plan if cash-flow issues
- Don't just ignore payment deadlines
Legitimate delays:
- Waiting for inspection (if contractor controls timing)
- Resolving defects
- Missing lien releases
- Contract disputes
Not legitimate:
- "I forgot"
- "I'm out of town"
- "I don't feel like paying yet"
- "I'm waiting for my construction loan" (arrange financing before committing)
Payment Disputes
What to do when you disagree about payment:
Common Disputes
- Work not complete to contractor's claim
- Quality not acceptable
- Amount owed differs between you and contractor
- Extras not approved but contractor wants paid
- Inspection failed, who pays to fix
Resolution Process
Step 1: Review contract
- What does contract say about this?
- Who's right according to contract?
- What's the dispute resolution process?
Step 2: Document your position
- Photos
- Contract references
- Inspector comments
- Cost to remedy
- Written summary
Step 3: Meet and discuss
- Professional, calm
- Focus on facts and contract
- Listen to their position
- Look for compromise
Step 4: Written resolution
- Document what you agree to
- Both sign
- Follow through
Step 5: Formal dispute resolution (if can't resolve)
- Mediation (neutral third party helps negotiate)
- Arbitration (neutral third party decides)
- Litigation (court, last resort)
Most disputes resolve at Step 3
Example Dispute Resolution
Issue: Framing contractor claims final payment ($3,000) is due. You see several punch-list items incomplete.
Wrong approach: Ignore their calls, refuse to pay, no explanation
Right approach:
- Create punch list with photos
- Email contractor: "I have the following items remaining per our contract before final payment: [list]. Once these are complete, I'll process payment within 5 days."
- Meet on site to review list
- Contractor completes items or you negotiate
- Verify completion
- Pay promptly
Resolution: Professional, documented, fair
Payment Records to Keep
For taxes, insurance, resale, legal protection:
Required Documentation
- All contracts
- All invoices
- All payment records (canceled checks, transfer confirmations)
- All lien releases
- All inspection approvals
- Photos of completed work
- Change orders
How Long to Keep
- Forever: Contracts, lien releases, major receipts
- 7 years minimum: For tax purposes
- Until you sell: To document improvements for capital gains
Organization System
/Project Name/
/Contracts/
Framing Contract - Signed.pdf
Plumbing Contract - Signed.pdf
/Payments/
Framing Payment 1 - $5000 - Check 1001.pdf
Framing Payment 2 - $5000 - Check 1015.pdf
/Lien Releases/
Framing - Conditional Release 1.pdf
Framing - Final Unconditional Release.pdf
/Inspections/
Framing Inspection - Passed 6-15-24.pdf
/Invoices/
[All invoices]
Payment Schedule Checklist
Before first payment:
- [ ] Contract signed by both parties
- [ ] Verified license and insurance
- [ ] Payment schedule clearly defined in contract
- [ ] Lien release forms prepared
Before each progress payment:
- [ ] Milestone actually achieved
- [ ] Work inspected personally
- [ ] Required inspections passed
- [ ] Photos taken and stored
- [ ] Conditional lien release signed
- [ ] No previous liens filed
- [ ] Payment amount matches contract
- [ ] Payment processed within agreed timeline
Before final payment:
- [ ] 100% of scope complete
- [ ] All punch-list items done
- [ ] Final inspection passed (if required)
- [ ] Unconditional lien release from contractor
- [ ] Lien releases from all subs/suppliers
- [ ] Warranty documents provided
- [ ] Site cleanup complete
- [ ] All documentation provided
- [ ] 30-day hold period considered
- [ ] No liens filed against property
Next Steps
Understanding payment practices also requires:
-
Contract Essentials → - What should be in your payment terms
-
Managing Subs → - Coordination with payment schedule
-
Dealing with Problems → - What to do when payment disputes arise
**Remember