Construction Schedule Template: Create Your Build Timeline
A good schedule is your roadmap through the construction process. It keeps you organized, helps you coordinate trades, and prevents costly delays.
This guide provides templates and step-by-step instructions for creating and managing your construction schedule.
Why You Need a Schedule
Without a schedule:
- Subcontractors showing up at wrong time
- Materials arriving too early or too late
- Not knowing what's next
- Reactive instead of proactive
- Constant surprises and delays
With a schedule:
- Everyone knows when they're needed
- Materials ordered with proper lead time
- You're 2-4 weeks ahead in planning
- Proactive problem-solving
- Smooth transitions between phases
Time to create: 4-8 hours initially Time to maintain: 1-2 hours per week Value: Saves 4-8 weeks of delays ($5,000-15,000)
Schedule Template Options
Option 1: Simple Spreadsheet (Recommended for Most)
Best for:
- Straightforward projects
- First-time owner-builders
- Those comfortable with Excel/Google Sheets
Pros:
- Easy to create and update
- Free
- Can share with subcontractors
- Customizable
Cons:
- Doesn't show dependencies visually
- Manual critical path calculation
- Harder to see big picture
Download: Google Sheets Template | Excel Template
Option 2: Gantt Chart
Best for:
- Visual learners
- Complex projects
- Those who want to see dependencies
Pros:
- Visual timeline
- Shows dependencies
- Highlights critical path
- Professional appearance
Cons:
- Learning curve
- Takes longer to set up
- Can be overkill for simple projects
Tools:
- Microsoft Project: $600+ (professional)
- Excel with Gantt template: Free
- GanttProject: Free open-source software
- Smartsheet: $10-30/month
- Monday.com: $10-20/month
Download: Excel Gantt Template | Google Sheets Gantt
Option 3: Simple Timeline (Easiest)
Best for:
- Very simple projects
- Those who want basic overview
- Quick planning
Pros:
- Extremely simple
- Quick to create
- Easy to understand
Cons:
- Not detailed enough for complex projects
- Hard to track details
- Limited usefulness for coordination
Download: PDF Timeline Template
Creating Your Schedule: Step-by-Step
Step 1: List All Major Tasks
Break your project into phases:
Pre-Construction:
- Feasibility and planning
- Design and engineering
- Permitting
Site Work:
- Site clearing
- Excavation and grading
- Utility rough-ins
- Temporary power
Foundation:
- Footings
- Foundation walls
- Waterproofing
- Backfill
Framing:
- Floor system
- Wall framing
- Roof framing
- Sheathing
- Windows and doors
- Dry-in (felt/housewrap)
Rough-Ins:
- HVAC rough-in
- Plumbing rough-in
- Electrical rough-in
- Inspections
Insulation & Drywall:
- Insulation
- Insulation inspection
- Drywall hang
- Drywall finish
Interior Finishes:
- Interior trim
- Cabinets
- Countertops
- Flooring
- Paint
- Tile
- Plumbing fixtures
- Electrical fixtures
Exterior Finishes:
- Siding
- Exterior trim
- Roofing
- Gutters
- Deck/porch
- Exterior paint
Final:
- Punch list
- Final cleaning
- Final inspection
- Landscaping
- Driveway
Step 2: Estimate Duration for Each Task
Use realistic estimates:
Example durations for 2,000 sq ft home:
| Task | Professional | Owner-Builder Hiring Out | Owner-Builder DIY |
|---|---|---|---|
| Foundation | 3-4 weeks | 4-5 weeks | 5-6 weeks |
| Framing | 4-6 weeks | 6-8 weeks | 10-14 weeks |
| Rough-ins | 4-6 weeks | 6-8 weeks | 8-12 weeks |
| Insulation/Drywall | 3-4 weeks | 4-5 weeks | 5-7 weeks |
| Interior finishes | 6-8 weeks | 8-10 weeks | 12-16 weeks |
| Exterior finishes | 4-6 weeks | 6-8 weeks | 8-12 weeks |
Add buffer:
- Owner-builder hiring out: Add 25% to professional estimates
- Owner-builder DIY: Add 50-100% to professional estimates
- Weather-dependent work: Add 20-30% for weather buffer
Be realistic: Better to finish early than constantly behind
Step 3: Identify Dependencies
For each task, ask: "What must be complete before this can start?"
Example dependencies:
| Task | Must Be Complete First |
|---|---|
| Framing | Foundation complete and inspected |
| Rough-ins | Framing complete, building dried in |
| Insulation | All rough-ins complete and inspected |
| Drywall | Insulation complete and inspected |
| Cabinets | Drywall finished and painted |
| Countertops | Cabinets installed |
| Flooring | Paint complete (typically) |
Some tasks can happen in parallel:
- Siding can happen during interior rough-ins
- Exterior finishes during interior finishes
- Different rooms can be at different stages
Step 4: Add Material Lead Times
Critical to schedule:
Order before phase starts:
| Material | Lead Time | Order When |
|---|---|---|
| Windows/doors | 8-12 weeks | Before framing starts |
| Trusses | 6-8 weeks | Before framing starts |
| HVAC equipment | 4-8 weeks | Before rough-in starts |
| Cabinets | 8-12 weeks | During framing |
| Countertops | 3-5 weeks | After cabinets installed (template) |
| Special flooring | 4-8 weeks | During drywall |
| Appliances | 4-6 weeks | During interior finishes |
Add these deadlines to your schedule
Step 5: Add Inspection Points
Schedule inspections:
| Inspection | When | Advance Notice Needed |
|---|---|---|
| Footing | Before concrete pour | 24-48 hours |
| Foundation | Before backfill | 24-48 hours |
| Framing | After dried in, before insulation | 24-48 hours |
| Rough plumbing | Before covering | 24-48 hours |
| Rough electrical | Before covering | 24-48 hours |
| Rough HVAC | Before covering | 24-48 hours |
| Insulation | Before drywall | 24-48 hours |
| Final | When 95%+ complete | 24-48 hours |
Build in correction time:
- 3-5 days after each inspection for potential failures
- Corrections
- Re-inspection
Step 6: Add Subcontractor Booking Deadlines
When to book each trade:
| Trade | Book How Far Ahead |
|---|---|
| Foundation | 6-8 weeks |
| Framing | 6-8 weeks |
| Roofing | 4-6 weeks |
| HVAC | 6-8 weeks |
| Plumbing | 6-8 weeks |
| Electrical | 6-8 weeks |
| Insulation | 4-6 weeks |
| Drywall | 4-6 weeks |
| Cabinets | 6-8 weeks |
| Flooring | 4-6 weeks |
| Tile | 4-6 weeks |
Add booking deadlines to schedule
Step 7: Identify Critical Path
Critical path = longest sequence of dependent tasks
Typical critical path: Foundation → Framing → Rough-ins → Insulation → Drywall → Cabinets → Countertops → Final
Mark these as high priority in your schedule
Step 8: Add Buffer Time
Where to add buffer:
- After each major phase: 3-5 days
- Weather-dependent phases: 20-30% additional time
- First-time DIY tasks: 50-100% additional time
- Before hard deadlines: 1-2 weeks
Overall buffer: 20-30% of total timeline
Example:
- Calculated timeline: 32 weeks
- Add 30% buffer: 42 weeks
- Planned completion: Week 42 (10 months)
Using the Spreadsheet Template
Setting Up
1. Download template: [Link to template]
2. Enter project info:
- Project name
- Address
- Start date
- Target completion date
3. Fill in task list:
- All tasks from Step 1
- Estimated duration for each
- Dependencies
4. Enter dates:
- Planned start date for each task
- Planned end date (based on duration)
5. Add contacts:
- Subcontractor for each task
- Contact info
- Booking status
6. Track materials:
- Required materials for each phase
- Order date
- Expected delivery
- Actual delivery
Weekly Updates
Every Friday (or Sunday):
1. Update completed tasks:
- Mark tasks complete
- Record actual completion date
- Note any issues
2. Review upcoming week:
- What's starting this week
- Confirm subcontractors
- Verify materials on-site
- Check prerequisites complete
3. Look ahead 2-4 weeks:
- What's coming up
- Book subcontractors if not done
- Order materials if not done
- Identify potential issues
4. Adjust dates:
- Update future dates based on current progress
- Account for any delays
- Notify affected subcontractors of changes
5. Communicate:
- Text upcoming week's subcontractors
- Confirm 2-4 weeks out with next round
- Update anyone affected by schedule changes
Time: 30-60 minutes per week
Using the Gantt Chart Template
Setting Up
1. Download template: [Link to template]
2. List all tasks in left column
3. Enter duration for each task
4. Set dependencies:
- Task B starts after Task A
- Use dependency column or linking
5. Add milestones:
- Permit approved
- Dried in
- Final inspection
6. Format:
- Color code by phase
- Highlight critical path (red)
- Mark current date
Reading Your Gantt Chart
Bars represent tasks:
- Length = duration
- Position = timing
- Overlap = parallel work
Dependencies shown with arrows:
- One task must finish before next starts
Critical path highlighted:
- Tasks that affect completion date
- No float/slack
Current date line:
- Shows where you are
- Tasks left of line should be complete
- Tasks on line should be in progress
Updating Gantt Chart
Weekly:
- Mark progress on each task (% complete)
- Update actual start/end dates
- Adjust future tasks based on current status
- Review critical path
When delays occur:
- Extend task bar
- Chart automatically adjusts downstream tasks
- See immediate impact on completion date
Sample Schedules by Project Type
2,000 sq ft Ranch, Owner-Builder Hiring Out (10-month timeline)
Month 1-2: Pre-construction and permitting
- Week 1-4: Planning and design
- Week 5-8: Permit application and approval
Month 3: Site work and foundation
- Week 9-10: Site work
- Week 11-13: Foundation
Month 4-5: Framing
- Week 14-19: Framing and dry-in
- Week 20: Framing inspection
Month 6-7: Rough-ins
- Week 21-22: HVAC rough-in
- Week 23-24: Plumbing rough-in
- Week 25-26: Electrical rough-in
- Week 27: Rough inspections
Month 7-8: Insulation and drywall
- Week 28: Insulation and inspection
- Week 29-32: Drywall
Month 8-10: Finishes
- Week 33-34: Interior trim
- Week 35-36: Cabinets and counters
- Week 37-38: Flooring and paint
- Week 39-40: Fixtures and final items
- Week 41-42: Final inspection and close-out
Parallel work: Exterior finishes (siding, roofing) during weeks 21-38
2,400 sq ft Two-Story, Part-Time Owner-Builder DIY (16-month timeline)
Month 1-3: Pre-construction and permitting
- Month 1: Planning
- Month 2-3: Permitting
Month 4: Site work and foundation start
- Weeks 1-2: Site work
- Weeks 3-4: Foundation start
Month 5: Foundation complete
- Weeks 1-4: Foundation finish and cure
Month 6-9: Framing (DIY)
- 16 weeks framing (weekends, part-time)
Month 10-11: Rough-ins (hired out)
- 8 weeks for HVAC, plumbing, electrical
Month 12: Insulation and drywall start
- Hired out
Month 13: Drywall complete
Month 14-16: Interior finishes
- Cabinets: Hired out (2 weeks)
- Counters: Hired out (1 week)
- Flooring: DIY (4 weeks)
- Paint: DIY (4 weeks)
- Trim: DIY (4 weeks)
- Many overlap
Month 14-16: Exterior finishes (parallel)
- Siding: Hired out
- Trim: DIY
Month 16: Final inspection and close-out
Schedule Management Tools
Digital Tools
Free:
- Google Sheets (spreadsheet)
- Excel (if you have it)
- GanttProject (open-source Gantt software)
- Trello (kanban-style task management)
Paid ($10-30/month):
- Smartsheet (collaborative Gantt)
- Monday.com (project management)
- Asana (task management)
- CoConstruct (construction-specific)
Professional ($600+):
- Microsoft Project (full project management)
Recommendation for most owner-builders: Google Sheets or Excel template (free, flexible, easy)
Communication Tools
For coordinating with subcontractors:
Text messaging:
- Create contact groups
- Quick updates and confirmations
- "Rough-in trades" group, "Finish trades" group
Shared calendar:
- Google Calendar
- Share with key subcontractors
- Everyone sees upcoming work
Photo documentation:
- Take photos at each phase
- Helps with questions
- Documents progress
- Timestamp with date
Tracking Tools
Budget vs. actual:
- Track estimated vs. actual costs by phase
- Identify where you're over/under
- Adjust future estimates
Timeline vs. actual:
- Track estimated vs. actual duration
- Learn your pacing
- Improve future estimates
Issues log:
- Track all problems and resolutions
- Learn from mistakes
- Reference for similar future issues
Common Scheduling Mistakes
Mistake #1: Creating Schedule and Never Updating
Problem: Schedule becomes meaningless after first week
Fix: Weekly updates, every Friday/Sunday, no exceptions
Mistake #2: No Buffer Time
Problem: Any delay cascades to completion
Fix: Add 20-30% buffer throughout
Mistake #3: Not Accounting for Lead Times
Problem: Material delays stop entire project
Fix: Add material ordering deadlines to schedule
Mistake #4: Ignoring Dependencies
Problem: Schedule tasks that can't actually happen yet
Fix: Clearly identify what must be complete first
Mistake #5: Too Much Detail
Problem: Spending hours tracking every small task
Fix: Focus on major phases and critical milestones, not daily tasks
Mistake #6: Not Sharing Schedule
Problem: Subcontractors don't know timeline
Fix: Share relevant portions with each trade, update them weekly
Mistake #7: Rigid Timeline
Problem: Can't adapt when delays occur (and they will)
Fix: Use schedule as guide, not gospel. Adjust as needed.
Schedule Review Checklist
Monthly, ask yourself:
- [ ] Is my schedule up to date?
- [ ] Am I on track for completion date?
- [ ] Are there any upcoming bottlenecks?
- [ ] Have I booked subcontractors 6-8 weeks ahead?
- [ ] Have I ordered materials with adequate lead time?
- [ ] Do subcontractors know when they're needed?
- [ ] Are there tasks I can do in parallel to save time?
- [ ] Is my critical path on track?
- [ ] What are my risks for the next 4-8 weeks?
- [ ] Do I need to adjust completion date expectations?
Key Takeaways
You need a schedule: It's your roadmap, prevents chaos
Keep it simple: Spreadsheet or basic Gantt is sufficient for most projects
Update weekly: Schedule only works if you maintain it
Focus on big picture: Major phases and milestones, not daily minutiae
Build in buffer: 20-30% overall, more for weather-dependent and DIY work
Track dependencies: Know what must be complete before next task
Add material deadlines: Order long-lead items with plenty of time
Share with team: Subcontractors need to know when they're needed
Be flexible: Schedule guides you, but adjust to reality
Review regularly: Weekly updates, monthly big-picture review
Template Downloads
Spreadsheet Templates:
- Google Sheets Template - Basic
- Excel Template - Basic
- Google Sheets Template - Advanced with Budget Tracking
Gantt Chart Templates:
PDF Templates:
Supporting Documents:
Related Resources
- Realistic Timeline Guide →
- Critical Path Method →
- Coordinating Trades →
- Material Lead Times →
- Common Delays →
Need help creating or managing your construction schedule? Our consulting services include personalized schedule development, critical path analysis, and ongoing schedule management for owner-builder projects.